08.01.2013 Views

Steel Designers Manual - TheBestFriend.org

Steel Designers Manual - TheBestFriend.org

Steel Designers Manual - TheBestFriend.org

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

This material is copyright - all rights reserved. Reproduced under licence from The <strong>Steel</strong> Construction Institute on 12/2/2007<br />

To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.<strong>org</strong>/<br />

<strong>Steel</strong> <strong>Designers</strong>' <strong>Manual</strong> - 6th Edition (2003)<br />

of delay caused by bad weather or insufficient or inadequate construction resources<br />

in the locality of the site are significantly reduced.<br />

Structural steel frameworks should generally be capable of being erected without<br />

temporary propping or scaffolding, although temporary bracing will be required,<br />

especially for welded frames.This applies particularly to the construction of the concrete<br />

slab, which should be self-supporting at all stages of erection. Permanent metal<br />

or precast concrete shutters should be used to support the in situ concrete.<br />

In order to allow a rapid start to construction, the structural steelwork frame<br />

should commence at foundation level, and preference should be given to single<br />

foundations for each column rather than raft or shared foundations (Fig. 2.12).<br />

Speed of erection is directly linked to the number of crane hours available. To<br />

reduce the number of lifts required on site, the number of elements forming the<br />

framework should be minimized within the lifting capacity of the craneage provided<br />

on site for other building components. For similar-sized buildings, the one with the<br />

longer spans and fewer elements will be the fastest to erect. However, as has been<br />

mentioned earlier, longer spans require deeper, heavier elements, which will<br />

increase the cost of raw materials and pose a greater obstruction to the distribution<br />

of building services, thereby requiring the element to be perforated or shaped and<br />

hence increasing the cost of fabrication.<br />

Columns are generally erected in multi-storey lengths: two is common and three<br />

is not unusual. The limitation on longer lengths is related more to erection than to<br />

restrictions on transportation, although for some urban locations length is a major<br />

consideration for accessibility.<br />

To provide rapid access to the framework the staircases should follow the erection<br />

of the frame. This is generally achieved by using prefabricated stairs which are<br />

detailed as part of the steel frame.<br />

The speed of installation of the following building elements is hastened if their<br />

connection and fixing details are considered at the same time as the structural steel<br />

frame design. In this way the details can be either incorporated in the framework<br />

or separated from it, whichever is the most effective overall: it is generally more<br />

efficient to separate the fixings and utilize the high inherent accuracy of the frame<br />

:'<br />

n 11<br />

n<br />

U__[[I<br />

a__U__[[I<br />

Li<br />

Fig. 2.12 Columns on large diameter bored piles<br />

Factors influencing choice of form 57

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!