Installation<br />
- Installing the Chiller<br />
Detailed information on installing and starting the chiller can be found in<br />
the manual supplied with the chiller.<br />
1. Place the chiller on the floor close enough to the <strong>Tsunami</strong> laser head<br />
so the 3.5 m long hoses will reach from the chiller connectors on the<br />
back of the unit to the <strong>Tsunami</strong> front bezel connectors.<br />
WARNING<br />
Do not place the chiller above the laser. Should the unit not be installed<br />
properly and a leak develop, dripping water may damage one or both<br />
lasers.<br />
2. Unscrew the knurled nuts holding the large barbed hose fittings to the<br />
back of the chiller and remove the barbed fittings.<br />
3. Find the two hoses in the accessory kit and locate the ends without<br />
fittings. Slide one of the knurled nuts just removed over each hose<br />
end with the threads facing the end of the hose.<br />
One end of each hose has a quick-disconnect fitting already attached.<br />
4. Find the two small, barbed hose fittings in the accessory kit and push<br />
them into the ends of the two hoses.<br />
It may be a tight fit. The polyurethane hose can be stretched either<br />
using long-nosed pliers or by warming the ends a little with a flameless<br />
heater. Note: overheating the hose will damage it and can result<br />
in leaks later.<br />
5. Screw both hoses onto the chiller and tighten.<br />
The hose connections are not polarized. Finger tight is enough: do not<br />
overtighten.<br />
6. Push the quick-disconnect fitting on the other hose end into either of<br />
the two water fittings on the <strong>Tsunami</strong> input bezel. When it seats, it<br />
will fasten with a click (refer to Figure 4-3).<br />
7. Turn on the chiller and verify water is flowing.<br />
Refer to the chiller manual for instructions.<br />
8. Inspect for leaks at the hose connections just made, and also inside<br />
the laser head where the polyurethane hoses attach to the front bezel<br />
and to the rod holder.<br />
9. Set the chiller temperature for 18 " C (64 O F).<br />
This completes the installation of the chiller.