Related Operational Action <strong>Plan</strong> VII.D: Creating 5-Year Technology <strong>Plan</strong> to Improve Productivity<br />

ADDRESSES <strong>BOCES</strong> GOAL(S):<br />

V. Resourcing and Operational Efficiency<br />

VI. Technology<br />

RESPONSIBLE ADMINISTRATORS:<br />

Director, Technology Integration<br />

COLLABORATOR(S):<br />

Asst. Director, Technology Integration<br />

Administrative Council<br />

Building / Program Administrators<br />

RELATED OPERATIONAL OBJECTIVE: By February <strong>2008</strong>, <strong>Eastern</strong> <strong>Suffolk</strong> <strong>BOCES</strong> will establish and begin implementation of a<br />

five-year technology plan designed to position the agency to leverage its existing technology in achieving increased productivity and<br />

to identify and implement new technologies that will further enhance productivity in the future.<br />

DESCRIPTIVE NARRATIVE: By February <strong>2008</strong>, the Office of Technology Integration will create and publish on the agency’s<br />

Intranet a five year technology plan. This plan will consist of various sections that document: the existing infrastructure; the inventory<br />

of hardware and software; the standards for acquisition of new hardware and software; the standards for use of the hardware,<br />

software and network; research and development; visions of the future; Implementation schedules and projected costs; and other<br />

assorted sections that will serve to advance the objective of increased productivity.<br />

ACTIVITIES<br />

Target Date<br />

for Completion Responsible Person/Group Status/Outcome<br />

1. Establish a preliminary plan outline 9/1/06 Dir., Technology Integration Completed<br />

2. Document existing infrastructure and inventories 9/1/06 Asst. Dir., Technology Integration Completed<br />

3. Create/revise written standards for hardware and<br />

9/1/07 Dir., Technology Integration Completed<br />

software acquisition<br />

Asst. Dir., Technology Integration<br />

4. Create/revise written standards for hardware /<br />

9/1/07 Dir., Technology Integration Completed<br />

software / network use<br />

Asst. Dir., Technology Integration<br />

5. Create a written process for research and<br />

development<br />

11/1/07 Dir., Technology Integration Completed<br />

6. Document potential / probable vision for the future<br />

including implications<br />

11/1/07 Dir., Technology Integration Completed<br />

7. Document implementation schedules and projected<br />

costs in detail for year 1 and in summary for years 2<br />

through 5<br />

7/1/08 Dir., Technology Integration Completed<br />

<strong>Strategic</strong> <strong>Plan</strong> <strong>2008</strong>-09 145