Related Operational Action <strong>Plan</strong> VII.D: Creating 5-Year Technology <strong>Plan</strong> to Improve Productivity<br />
ADDRESSES <strong>BOCES</strong> GOAL(S):<br />
V. Resourcing and Operational Efficiency<br />
VI. Technology<br />
RESPONSIBLE ADMINISTRATORS:<br />
Director, Technology Integration<br />
COLLABORATOR(S):<br />
Asst. Director, Technology Integration<br />
Administrative Council<br />
Building / Program Administrators<br />
RELATED OPERATIONAL OBJECTIVE: By February <strong>2008</strong>, <strong>Eastern</strong> <strong>Suffolk</strong> <strong>BOCES</strong> will establish and begin implementation of a<br />
five-year technology plan designed to position the agency to leverage its existing technology in achieving increased productivity and<br />
to identify and implement new technologies that will further enhance productivity in the future.<br />
DESCRIPTIVE NARRATIVE: By February <strong>2008</strong>, the Office of Technology Integration will create and publish on the agency’s<br />
Intranet a five year technology plan. This plan will consist of various sections that document: the existing infrastructure; the inventory<br />
of hardware and software; the standards for acquisition of new hardware and software; the standards for use of the hardware,<br />
software and network; research and development; visions of the future; Implementation schedules and projected costs; and other<br />
assorted sections that will serve to advance the objective of increased productivity.<br />
ACTIVITIES<br />
Target Date<br />
for Completion Responsible Person/Group Status/Outcome<br />
1. Establish a preliminary plan outline 9/1/06 Dir., Technology Integration Completed<br />
2. Document existing infrastructure and inventories 9/1/06 Asst. Dir., Technology Integration Completed<br />
3. Create/revise written standards for hardware and<br />
9/1/07 Dir., Technology Integration Completed<br />
software acquisition<br />
Asst. Dir., Technology Integration<br />
4. Create/revise written standards for hardware /<br />
9/1/07 Dir., Technology Integration Completed<br />
software / network use<br />
Asst. Dir., Technology Integration<br />
5. Create a written process for research and<br />
development<br />
11/1/07 Dir., Technology Integration Completed<br />
6. Document potential / probable vision for the future<br />
including implications<br />
11/1/07 Dir., Technology Integration Completed<br />
7. Document implementation schedules and projected<br />
costs in detail for year 1 and in summary for years 2<br />
through 5<br />
7/1/08 Dir., Technology Integration Completed<br />
<strong>Strategic</strong> <strong>Plan</strong> <strong>2008</strong>-09 145