<strong>Ordinary</strong> <strong>Meeting</strong> <strong>of</strong> <strong>Council</strong> - <strong>27</strong> <strong>February</strong> <strong>2007</strong> 2 / 41<br />
20 to 22 Tryon Road, Lindfield<br />
Item 2<br />
DA0826/06<br />
22 January <strong>2007</strong><br />
77. The following tree species shall be planted, at no cost to <strong>Council</strong>, in the nature strip fronting<br />
the property along Tryon Road as an evenly spaced avenue planting. The tree/s used shall be<br />
a minimum 25 litres container size specimen/s trees:<br />
Tree Species<br />
Quantity<br />
Lophostemon confertus (Brushbox) 3<br />
78. The following tree species shall be planted, at no cost to <strong>Council</strong>, in the nature strip fronting<br />
the property along Tryon Road as an evenly spaced avenue planting. The tree/s used shall be<br />
a minimum 25 litres container size specimen/s trees:<br />
Tree Species<br />
Quantity<br />
Lophostemon confertus (Brushbox) 5<br />
79. All builders' refuse, spoil and/or material unsuitable for use in landscape areas shall be<br />
removed from the site on completion <strong>of</strong> the building works.<br />
80. The canopy replenishment trees to be planted shall be maintained in a healthy and vigorous<br />
condition until they attain a height <strong>of</strong> 5.0 metres whereby they will be protected by <strong>Council</strong>’s<br />
Tree Preservation Order. Any <strong>of</strong> the trees found faulty, damaged, dying or dead shall be<br />
replaced with the same species.<br />
CONDITIONS TO BE COMPLIED WITH PRIOR TO THE ISSUE OF A CONSTRUCTION<br />
CERTIFICATE<br />
81. Critical Stage Inspections for Building Work (Class 2):<br />
Where applicable inspections <strong>of</strong> the development site may be required to be undertaken at the<br />
following stages:<br />
a) At the commencement <strong>of</strong> the building work; and<br />
b) Prior to covering <strong>of</strong> waterpro<strong>of</strong>ing in any wet areas, for a minimum <strong>of</strong> 10 percent <strong>of</strong><br />
rooms with wet areas within a building; and<br />
c) Prior to covering any stormwater lines/connections; and<br />
d) After the building work has been completed and prior to any occupation certificate<br />
being issued in relation to the building.<br />
e) Other inspection required by PCA<br />
Critical Stage Inspections for Building Work (Class 7):<br />
Where applicable inspections <strong>of</strong> the development site may be required to be undertaken at the<br />
following stages:<br />
a) At the commencement <strong>of</strong> the building work; and<br />
b) Prior to covering any stormwater drainage lines/connections; and<br />
c) After the building work has been completed and prior to any occupation certificate<br />
issued in relation to the building;<br />
d) Other inspection as required by the PCA.<br />
N:\0702<strong>27</strong>-OMC-PR-03642-20 TO 22 TRYON ROAD LINDF.doc/pdonnelly/41