intent. The CC also makes sure that during verification testing, the temperature, pressure, fluid flow,<br />

control system signals, <strong>and</strong> actions are commissionable <strong>and</strong> included in the design.<br />

Second, postconstruction commissioning is most prevalent recently. Postconstruction commissioning<br />

<strong>of</strong>ten requires at least 1 year after the completion <strong>of</strong> the construction so that both summer<br />

cooling <strong>and</strong> winter heating mode operations can be included. In this case, the commission consultant<br />

is most <strong>of</strong>ten an outsider who was not involved in the problems <strong>and</strong> politics <strong>of</strong> the design <strong>and</strong><br />

construction. Therefore, conciliatory <strong>and</strong> pr<strong>of</strong>essional interpersonal skills are extremely important<br />

for a CC. The CC also will learn about, evaluate, test, <strong>and</strong> document the installed HVAC&R system<br />

<strong>and</strong> become involved in the operators’ training.<br />

Third, existing building recommissioning helps to reduce HVAC&R energy consumption, improves<br />

IAQ, <strong>and</strong> improves indoor environmental control.<br />

Cost <strong>of</strong> HVAC&R Commissioning<br />

Because the HVAC&R commissioning process is still being developed <strong>and</strong> st<strong>and</strong>ardized, a rule <strong>of</strong><br />

thumb for HVAC&R commissioning cost is between 2 <strong>and</strong> 5 percent <strong>of</strong> the construction cost <strong>of</strong> the<br />

systems to be commissioned. The cost <strong>of</strong> HVAC&R commissioning can be set aside as an independent<br />

budget item or added to the architectural/engineering or contractor fees. The commissioning<br />

cost will be recovered by reductions in change orders <strong>and</strong> claims.<br />

32.2 HVAC&R MAINTENANCE<br />

Basics<br />

HVAC&R maintenance is the work required to maintain or restore HVAC&R systems, including<br />

equipment, instrumentation, components, <strong>and</strong> materials, to condition such that they can be effectively<br />

operated to meet specified requirements.<br />

ASHRAE <strong>H<strong>and</strong>book</strong> 1999, HVAC Applications, defines rep<strong>air</strong> as to make good or restore to<br />

good or sound conditions, <strong>and</strong> defines service as what is necessary to effect a maintenance program<br />

short <strong>of</strong> rep<strong>air</strong>. In the ASHRAE h<strong>and</strong>book, maintenance also is classified into the following categories:<br />

● Run-to-failure is a kind <strong>of</strong> arrangement such that no money is spent on maintenance prior to<br />

equipment or system breakdown.<br />

● In planned maintenance, all functions <strong>and</strong> resources in this category must be planned, budgeted,<br />

<strong>and</strong> scheduled. Planned maintenance can be subdivided into preventive <strong>and</strong> corrective maintenance.<br />

Preventive maintenance is a kind <strong>of</strong> scheduled maintenance for an HVAC&R system,<br />

equipment, or components, in order to maintain durability, reliability, efficiency, <strong>and</strong> safety. In<br />

corrective maintenance, corrective action is <strong>of</strong>ten the remedial action performed before failure occurs.<br />

Corrective action taken during a shutdown in response to a failure is called a rep<strong>air</strong>.<br />

● Predictive maintenance is based on equipment <strong>and</strong> system monitoring, the operating conditions,<br />

<strong>and</strong> performance to discover faults <strong>and</strong> degradations <strong>and</strong> thus the remedy performed.<br />

Most manufacturers give detailed instructions in how to operate <strong>and</strong> maintain the specific equipment<br />

<strong>and</strong> instruments. These instructions must be followed.<br />

Maintenance Contractors <strong>and</strong> Maintenance Personnel<br />

COMMISSIONING AND MAINTENANCE 32.5<br />

In most small facilities with comparatively simple HVAC&R systems, outside maintenance contractors<br />

<strong>of</strong>ten provide maintenance service based on the specified maintenance program. The time inter-