Exhibit 2<br />

Page 13 of 379<br />

Terminal 4 Gate Replacement – Western Expansion<br />

3.1.5 <strong>COUNTY</strong> underst<strong>and</strong>s that the Project will be subject to the LEED-certification<br />

process <strong>and</strong> procedures as determined by the USGBC. These procedures are<br />

outside the control of CONTRACTOR, may not be uniformly implemented <strong>and</strong> may<br />

be subject to change at any time.<br />

3.1.6 CONTRACTOR cannot guarantee LEED certification or the actual performance of<br />

the building based on CONTRACTOR’s efforts nor can it guarantee certain<br />

performance levels anticipated through the LEED-certification process.<br />

3.1.7 Notwithst<strong>and</strong>ing the preceding paragraphs, Consultant shall remain responsible for<br />

submitting complete <strong>and</strong> thorough documents <strong>and</strong> materials to the USGBC in a<br />

timely manner. While the LEED certification of the Project cannot be guaranteed, the<br />

CONTRACTOR shall carry out all of the responsibilities as the contractor on a LEED<br />

project for the <strong>COUNTY</strong> <strong>and</strong> will continue throughout the LEED certification process<br />

including commissioning for LEED purposes. Only decisions made by the <strong>COUNTY</strong><br />

that prevent the CONTRACTOR from obtaining LEED certification shall be grounds<br />

for not obtaining LEED certification of the Project.<br />

3.2 It is the intent of <strong>COUNTY</strong> to describe in the Contract Documents a functionally complete<br />

Project (or part thereof) to be constructed in accordance with the Contract Documents.<br />

Any Work, materials or equipment that may reasonably be inferred from the Contract<br />

Documents as being required to produce the intended result shall be supplied by<br />

CONTRACTOR, whether or not specifically called for by the Contract Documents. When<br />

words, which have a well-known technical or trade meaning are used to describe Work,<br />

materials or equipment, such words shall be interpreted in accordance with that meaning.<br />

Reference to st<strong>and</strong>ard specifications, manuals, or codes of any technical society,<br />

organization or association, or to the laws or regulations of any governmental authority,<br />

whether such reference be specific or by implication, shall mean the latest st<strong>and</strong>ard<br />

specification, manual, code or laws or regulations in effect at the time of permit issuance.<br />

<strong>COUNTY</strong> shall have no duties other than those duties <strong>and</strong> obligations expressly set forth<br />

within the Contract Documents.<br />

3.3 The CONTRACTOR agrees that the Work shall be performed in a good <strong>and</strong> professional<br />

manner, free from defects in materials <strong>and</strong> workmanship, <strong>and</strong> that all materials shall be new<br />

<strong>and</strong> approved by the Consultant <strong>and</strong> all workmanship shall be acceptable to the CPM,<br />

except as otherwise expressly provided for in the Contract Documents. The CONTRACTOR<br />

shall cause all materials <strong>and</strong> other parts of the Work to be readily available as <strong>and</strong> when<br />

required or needed for or in connection with the construction, furnishing <strong>and</strong> equipping of the<br />

improvements.<br />

3.4 The CONTRACTOR shall plan, record, <strong>and</strong> update, at least monthly through Final<br />

Completion, the construction Baseline Schedule of the Project compatible or convertible to<br />

Primavera P6. The progress schedule shall indicate the dates for the commencement <strong>and</strong><br />

completion of the various stages of construction <strong>and</strong> shall be updated as required by the<br />

Contract Documents. The Progress Schedule shall encompass all of the work of all trades<br />

necessary for the construction of the Project <strong>and</strong> shall be sufficiently complete <strong>and</strong><br />

comprehensive to enable progress to be monitored through the end of the warranty phase of<br />

the Project. The Progress Schedule shall incorporate sufficient time for important <strong>COUNTY</strong><br />