DIVISION 1 SPECIFICATIONS<br />

SECTION 01315 PROGRESS SCHEDULES (COMPUTERIZED CPM)<br />

c. Labor trades involved in performing work<br />

d. Submittal, review, procurement, fabrication, delivery, installation,<br />

<strong>and</strong> testing of major materials <strong>and</strong> equipment<br />

e. Delivery / Installation of County-furnished equipment<br />

f. Interfaces <strong>and</strong> dependencies with preceding, concurrent, <strong>and</strong><br />

follow-on contractors<br />

g. Plans for subcontract work<br />

h. Manpower, material <strong>and</strong> equipment restrictions<br />

i. Commissioning / Close Out Processes<br />

j. Contract milestones <strong>and</strong> phasing<br />

k. Allow for holidays, vacations <strong>and</strong> non-work days applicable to the<br />

schedule<br />

D. SUMMARY BAR CHART<br />

1. The Summary Bar Chart shall be based on activity durations <strong>and</strong> logic<br />

indicated on the Baseline Schedule <strong>and</strong> Updated Progress Schedules.<br />

2. The CONTRACTOR <strong>and</strong> the CPM shall jointly select summary level<br />

activities.<br />

3. Each summary level activity shall include:<br />

a. A concise description of the Work represented by the activity.<br />

b. A time bar indicating planned / actual activity start <strong>and</strong> finish dates<br />

<strong>and</strong> actual cumulative percent complete at the end of each<br />

monthly reporting period.<br />

c. A status line as of the end of the reporting period.<br />

E. TWO WEEK LOOK-AHEAD SCHEDULE<br />

1. CONTRACTOR shall provide copies of applicable sections of any<br />

Baseline Schedule at the weekly progress meetings to show the<br />

subsequent Work to be performed during the next two weeks. Such 2-<br />

week look ahead schedules shall be further detailed to include<br />

coordination activities necessary to perform the work in accordance with<br />

the Contract Documents.<br />

F. SCHEDULE REVIEW AND APPROVAL<br />

Exhibit 2<br />

Page 264 of 379<br />

1. The CONTRACTOR <strong>and</strong> the CPM shall meet within seven (7) calendar<br />

days of receipt of the CONTRACTOR’s Preliminary Baseline Schedule<br />

Submittal for joint review of the proposed Preliminary Baseline Schedule.<br />

The CONTRACTOR shall revise any areas, which, in the opinion of the<br />

CPM, conflict with either the intent of this Section or the timely completion<br />

of the Project.<br />

2. In the event the CONTRACTOR fails to define any element of work<br />

activity or logic currently designed <strong>and</strong> the CPM’s review does not detect<br />

this omission or error, such omission or error, when discovered by the<br />

CONTRACTOR or the CPM, shall be corrected by the CONTRACTOR at<br />

the next Updated Progress Schedule (discussed hereinafter).<br />

Section 01315 Progress Schedule (Computerized CPM) Page 59