DIVISION 1 SPECIFICATIONS<br />

SECTION 01340 – SHOP DRAWINGS, PRODUCT DATA AND SAMPLES<br />

F. Submittals that are received from sources other than through CONTRACTOR’s<br />

office will be returned without action. Delays resulting there from shall be<br />

CONTRACTOR’s responsibility.<br />

G. Package each submittal appropriately for transmittal <strong>and</strong> h<strong>and</strong>ling.<br />

H. Distribute reproductions of shop drawings, copies of product data, <strong>and</strong> samples,<br />

which bear CONSULTANT’s stamp of approval, to jobsite file, record documents<br />

file, subcontractors, suppliers <strong>and</strong> other entities requiring information.<br />

I. Do not fabricate products or begin work, which required submittals until return of<br />

submittal with CONSULTANT’s <strong>and</strong> CPM’s acceptance.<br />

1.07 CPM’S AND CONSULTANT’S ACTION:<br />

A. Where action <strong>and</strong> return is required or requested, CONSULTANT will review<br />

each submittal, mark with action, <strong>and</strong> where possible return with reasonable<br />

promptness. CPM will forward all comments to the CONSULTANT<br />

1. Where submittal must be held for coordination, CONTRACTOR will be so<br />

advised by the CONSULTANT.<br />

2. Affix stamp <strong>and</strong> initial or sign, <strong>and</strong> indicate requirements for resubmittal,<br />

or acceptance of submittal.<br />

3. Return submittals to CONTRACTOR for distribution or for resubmission.<br />

4. CONSULTANT will review submittals for design content only. CPM will<br />

review submittals for construction <strong>and</strong> installation considerations.<br />

B. Final Unrestricted Release: When submittal is returned marked “No Exceptions<br />

Taken”, work may proceed, provided it complies with Contract Documents.<br />

C. Final-But-Restricted-Release: When submittal is returned marked “Note<br />

Markings”, Work may proceed, provided it complies with notations <strong>and</strong><br />

corrections on submittal <strong>and</strong> with Contract Documents.<br />

D. Returned for Resubmittal:<br />

Exhibit 2<br />

Page 282 of 379<br />

1. When submittal is returned marked “Revise <strong>and</strong> Resubmit” or is<br />

unmarked, do not proceed with Work.<br />

2. Revise submittal in accordance with notations <strong>and</strong> resubmit without delay<br />

to obtain difference action marking.<br />

E. Other Action: Where submittal is returned for other reasons, with the CPM or<br />

CONSULTANT’s explanation included, it will be marked “Not Accepted”.<br />

PART 2 - PRODUCTS<br />

PART 3 - EXECUTION<br />

(Not Used)<br />

(Not Used)<br />

ATTACHMENTS:<br />

Submittal Transmittal<br />

Section 01340 Shop Drawings, Product Data <strong>and</strong> Samples Page 77

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!