Terminal 4 Gate Replacement – Western Expansion<br />

<strong>COUNTY</strong> or its representatives from inquiring into allegations of nonpayment. The<br />

foregoing remedies under this subsection 32.2.6 shall not be employed when<br />

CONTRACTOR demonstrates that failure to pay results from a bona fide dispute<br />

with its Subcontractor.<br />

32.2.7 <strong>COUNTY</strong> shall have access without limitation to CONTRACTOR’s books <strong>and</strong><br />

records including payroll records, tax returns <strong>and</strong> records, <strong>and</strong> books of account,<br />

on five (5) business day's notice, to allow <strong>COUNTY</strong> to determine<br />

CONTRACTOR’s compliance with its commitment to CBE participation <strong>and</strong> the<br />

status of any CBE firm performing any portion of this Agreement. On-site reviews<br />

to monitor the CONTRACTOR’s progress in achieving <strong>and</strong> maintaining CBE<br />

obligations will be carried out by the CA in conjunction with OESBD (or designee).<br />

32.2.8 If CONTRACTOR fails to comply with the requirements of this Agreement or the<br />

requirements of the County Business Enterprise Act of 2009, <strong>COUNTY</strong> shall have<br />

the right to exercise any administrative remedies provided by the Business<br />

Opportunity Act of 2004, or any other right or remedy provided in this Agreement<br />

or under applicable law, with all such rights <strong>and</strong> remedies being cumulative.<br />

32.3 CONTRACTOR Payment to Subcontractor<br />

32.3.1 CONTRACTOR shall pay its Subcontractors <strong>and</strong> suppliers within seven (7)<br />

calendar days following receipt of payment from the <strong>COUNTY</strong> for such<br />

subcontracted work or supplies. CONTRACTOR agrees that if it withholds an<br />

amount as retainage from its Subcontractors or suppliers, that it will release such<br />

retainage <strong>and</strong> pay same within seven (7) calendar days following receipt of<br />

payment of retained amounts from <strong>COUNTY</strong>, or within seven (7) calendar days<br />

after the Subcontractor has satisfactorily completed its work, for which the<br />

<strong>COUNTY</strong> has accepted through approval of CONTRACTOR’s application for<br />

payment.<br />

32.3.2 CONTRACTOR agrees that nonpayment of a Subcontractor or supplier as<br />

required above, shall be a material breach of this Agreement <strong>and</strong> that <strong>COUNTY</strong><br />

may, at its option, increase allowable retainage or withhold progress payments<br />

unless <strong>and</strong> until CONTRACTOR demonstrates timely payments of sums due to<br />

such Subcontractors or suppliers. CONTRACTOR agrees that the presence of a<br />

“pay when paid” provision in a subcontract shall not preclude <strong>COUNTY</strong>’s inquiry<br />

into allegations of nonpayment. The foregoing remedies shall not be employed<br />

when CONTRACTOR demonstrates that failure to pay results from a bona fide<br />

dispute with its Subcontractor or supplier.<br />

32.4 CONTRACT COMPLIANCE MONITORING<br />

32.4.1 CONTRACTOR agrees to submit monthly the CBE Utilization Report to OESBD,<br />

with copy to the PMO, containing a record of payments made to its CBE<br />

subcontractors during the current reporting period.<br />

32.4.2 CONTRACTOR agrees to submit the Final CBE Participation Report containing<br />

the total amount paid to its CBE subcontractors. This report must be submitted<br />

CM @ Risk Agreement R0787918R1 Page 74 of 85

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!