DIVISION 1 SPECIFICATIONS<br />

SECTION 01540 CONSTRUCTION SAFETY PLAN AND SECURITY REQUIREMENTS<br />

a. Prior to the commencement of any demolition or other Work,<br />

which will cause an interruption, or modification to existing aircraft<br />

operations, the CONTRACTOR shall confer with <strong>and</strong> obtain,<br />

written authorization from the CPM.<br />

b. If the CONTRACTOR requires access to operational areas not<br />

delineated on the Construction Safety Plan Drawing(s), the<br />

CONTRACTOR shall participate in negotiations leading to the<br />

imposition of restrictions on airport operations in the affected<br />

areas, he shall strictly abide by all conditions imposed by BCAD<br />

relating to his entry <strong>and</strong> use of such area <strong>and</strong> he shall not enter<br />

these areas until granted temporary, conditional entry clearance<br />

BCAD – Operations.<br />

c. Trenching, excavation <strong>and</strong> other work requiring temporary runway<br />

or taxiway closure shall be limited by the CONTRACTOR to that<br />

amount of work that can be completed within the hours of minimal<br />

operation. All ditches, excavations, etc. shall be restored prior to<br />

the end of the Work period <strong>and</strong> affected pavements returned to<br />

service. This Work shall be scheduled during hours of minimal<br />

operations. Hours of minimal operation shall be the hours<br />

<strong>between</strong> 10:00 p.m. <strong>and</strong> 6:00 a.m. All other hours shall be hours<br />

of normal operation.<br />

d. The CONTRACTOR may be required to pursue affected portions<br />

of the Work on a continuous 24-hour per day basis during<br />

construction of the various phases <strong>and</strong> subphases shown on the<br />

Drawings <strong>and</strong> described in the Contract Documents (such as<br />

when runways or taxiways, aprons, service or other access<br />

roadways, service gates are closed for operations or when<br />

hazards of any kind arise).<br />

e. The CPM will arrange with BCAD Operations for inspection prior<br />

to opening for aircraft use any taxiway that has been used for a<br />

crossing point or haul route by the CONTRACTOR.<br />

4. Operations Safety Inspection:<br />

Exhibit 2<br />

Page 305 of 379<br />

a. The entire Work Site shall be inspected daily <strong>and</strong> more frequently<br />

if construction activities are of a nature that debris may<br />

accumulate on AOA pavements. Special inspections shall be<br />

conducted for each Work Area prior to return to service for aircraft<br />

operation. The purpose of these inspections is to ascertain that<br />

areas returned to aircraft service are in satisfactory condition <strong>and</strong><br />

that the overall Work Site <strong>and</strong> its activities are within the safety<br />

criteria set forth in these Contract Documents. Inspections shall<br />

be conducted jointly by representatives of the CONTRACTOR,<br />

BCAD-Operations, the CPM <strong>and</strong> the airlines.<br />

b. Any violations of safety criteria found during these inspections<br />

shall be rectified immediately. If a violation cannot be corrected<br />

on an immediate basis by the CONTRACTOR, he shall<br />

immediately notify the CPM. No areas shall be approved for<br />

operations with violations occurring unless specifically authorized<br />

by BCAD-Operations, the CPM <strong>and</strong> the designated airline<br />

Section 01540 Construction Plan <strong>and</strong> Safety Requirements Page 100