DIVISION 1 SPECIFICATIONS<br />

SECTION 01255 CPEAM PROCEDURES<br />

Exhibit 2<br />

Page 242 of 379<br />

PART 1 GENERAL<br />

1.01 SUBMITIALS<br />

Submit name of the individual authorized to execute CPEAM documents, <strong>and</strong> be<br />

responsible for informing others in Contractor's employ or Subcontractors of<br />

changes to the Contract Price Elements <strong>and</strong> the Work.<br />

1.02 DOCUMENTATION OF CHANGE IN CONTRACT PRICE ELEMENTS<br />

A. Maintain detailed written daily records of the Work, Provide full information<br />

required for evaluation of proposed changes, <strong>and</strong> to substantiate costs <strong>and</strong> time<br />

adjustments as may be necessitated by changes in the Contract Price Elements.<br />

B. Document each quotation for a change in cost or time with sufficient data to allow<br />

evaluation of the quotation. Provide additional data as requested by the CPM.<br />

C. For all proposed changes to the Contract Price Elements, provide additional data<br />

to support computations:<br />

1. Quantities of products, labor, <strong>and</strong> equipment.<br />

2. Taxes, insurance, <strong>and</strong> bonds.<br />

3. Overhead <strong>and</strong> profit.<br />

4. Justification for any change in Contract Time.<br />

5. Credit for deletions from Contract, similarly documented.<br />

6. Bid Tabulation Sheets<br />

D. Time Impact Analysis:<br />

1. For all proposed CPEAM's where a change of project time is anticipated,<br />

Contractor shall prepare <strong>and</strong> submit a Time Impact Analysis illustrating<br />

the influence of each change upon the current Baseline Schedule. The<br />

Time Impact Analysis shall document:<br />

a. A schedule sub-net demonstrating how the Contractor proposes to<br />

incorporate the Work of a proposed change of Contract Price<br />

Element into the Baseline Schedule based upon the anticipated<br />

date an authorizing CPEAM is issued to the Contractor.<br />

b. The status of construction at that point in time<br />

c. The start/finish dates of all affected critical path activities utilizing<br />

the dates included in the latest updated detailed construction<br />

schedule closest to proposed change of Contract Price<br />

Element(s).<br />

2. Submit the Time Impact Analysis as an attachment to each submitted<br />

Document, 01260B Change Order Request (Proposal).<br />

3. When the Contractor does not submit a Time Impact Analysis for a<br />

Section 01255 CPEAM Procedures Page 37