Exhibit 2<br />

Page 37 of 379<br />

Terminal 4 Gate Replacement – Western Expansion<br />

schedule. CA may request CONTRACTOR to submit additional information<br />

to support its Application for Payment;<br />

as applicable, a consent of the surety as to release of final payment or<br />

release of retainage; <strong>and</strong><br />

Time sheets for management services in a form acceptable to the CA.<br />

.<br />

8.6.3 Ten percent (10%) of all monies earned by CONTRACTOR shall be retained by<br />

<strong>COUNTY</strong> until 50% of the Work is completed <strong>and</strong> accepted by the CA, excluding<br />

General Conditions. After fifty percent (50%) of the Work has been completed,<br />

the CONTRACTOR may request <strong>and</strong> the CA shall reduce the retainage to five<br />

percent (5%) of all monies previously earned <strong>and</strong> all monies earned thereafter,<br />

except CONTRACTOR’s General Conditions, with consent <strong>and</strong> release of<br />

Surety. After ninety percent (90%) of the Work has been completed, the<br />

CONTRACTOR may request <strong>and</strong> the CA may reduce the retainage to two <strong>and</strong><br />

one-half percent (2-1/2%) of all monies previously earned <strong>and</strong> all monies earned<br />

thereafter, except CONTRACTOR’s General Conditions, with consent <strong>and</strong><br />

release of Surety. Nothing contained herein; however, requires the <strong>COUNTY</strong> to<br />

pay or release any amounts that are the subject of a good faith dispute, the<br />

subject of a claim brought pursuant to s. 255.05, Florida Statutes, or otherwise<br />

the subject of a claim or dem<strong>and</strong> by the <strong>COUNTY</strong> or CONTRACTOR.<br />

8.6.4 Subsequent to Final Completion <strong>and</strong> prior to Final Payment, CA may reduce<br />

retainage to a nominal amount at the sole discretion of the CA. Any reduction in<br />

retainage shall be in the sole discretion of the CA, shall be recommended by<br />

PMO <strong>and</strong> CPM <strong>and</strong> CONTRACTOR shall have no entitlement to a reduction. In<br />

addition, the CA may authorize release of retainage as to a particular<br />

Subcontractor or trade when the work of that Subcontractor or trade is<br />

satisfactorily completed. Any interest earned on retainage shall accrue solely to<br />

the benefit of <strong>COUNTY</strong>. CA may require consent of Surety prior to any release or<br />

reduction of retainage.<br />

8.6.5 <strong>COUNTY</strong> may withhold, in whole or in part, payment to such extent as may be<br />

necessary to protect itself from:<br />

8.6.5.1 Defective CONTRACTOR or Subcontractor Work not remedied.<br />

8.6.5.2 Claims filed or reasonable evidence indicating probable filing of claims by<br />

other parties against CONTRACTOR.<br />

8.6.5.3 Failure of CONTRACTOR to make payments properly to Subcontractors<br />

or for material or labor.<br />

8.6.5.4 Damage to another contractor not remedied.<br />

8.6.5.5 Liquidated damages <strong>and</strong> costs incurred by PMO, CPM, <strong>COUNTY</strong> or<br />

Consultant for extended construction administration.<br />

8.6.5.6 Failure of CONTRACTOR to provide any <strong>and</strong> all documents required to<br />

be provided to <strong>COUNTY</strong> by the terms of the Contract Documents.<br />

CM @ Risk Agreement R0787918R1 Page 36 of 85