Exhibit 2<br />

Page 78 of 379<br />

Terminal 4 Gate Replacement – Western Expansion<br />

to establish a preliminary list of emergency recovery activities that the<br />

CONTRACTOR shall undertake.<br />

33.2.1.2 CONTRACTOR <strong>and</strong> CA shall utilize that preliminary list of emergency<br />

recovery activities to develop one or more Construction Change<br />

Directives for execution by the CA <strong>and</strong> CONTRACTOR. Upon mutual<br />

agreement, CA shall issue the executed Field Orders upon receipt of<br />

which, CONTRACTOR shall immediately undertake the emergency<br />

actions described therein.<br />

33.2.1.3 CONTRACTOR shall mobilize personnel, Subcontractors <strong>and</strong><br />

equipment as necessary to complete the tasks required by a Field<br />

Order for hurricane or other disaster recovery.<br />

33.2.1.4 <strong>COUNTY</strong> shall issue Purchase Orders <strong>and</strong> other procurement<br />

documents as necessary to support of Construction Change<br />

Directives as issued by the Contract Administrator.<br />

33.2.1.5 Prior to being eligible for payment of expenses due to Hurricane, pre<br />

or post, procedures, CONTRACTOR shall maintain detailed records<br />

of the Work <strong>and</strong> provide full information required for evaluation <strong>and</strong> to<br />

substantiate costs <strong>and</strong> time adjustments as may be necessitated by<br />

these required changes in the Work.<br />

33.2.1.6 CONTRACTOR shall coordinate invoicing <strong>and</strong> payment procedures<br />

for emergency recovery work with the CA to ensure expeditious<br />

payment <strong>and</strong> segregation of such payments from those applicable to<br />

the non-emergency Work required by this Agreement.<br />

ARTICLE 34 - OTHER TERMS & CONDITIONS<br />

34.1 Third Party Beneficiaries: Neither CONTRACTOR nor <strong>COUNTY</strong> intend to directly or<br />

substantially benefit a third party by this Agreement. Therefore, the parties agree that<br />

there are no third party beneficiaries to this Agreement <strong>and</strong> that no third party shall be<br />

entitled to assert a claim against either of them based upon this Agreement. The parties<br />

expressly acknowledge that it is not their intent to create any rights or obligations in any<br />

third person or entity under this Agreement.<br />

34.2 Conflicts: Neither CONTRACTOR nor its employees shall have or hold any continuing<br />

or frequently recurring employment or contractual relationship that is substantially<br />

antagonistic or incompatible with CONTRACTOR’s loyal <strong>and</strong> conscientious exercise of<br />

judgment related to its performance under this Agreement. CONTRACTOR agrees that<br />

none of its employees shall, during the term of this Agreement, serve as an adverse or<br />

hostile witness against <strong>COUNTY</strong> in any legal or administrative proceeding in which he or<br />

she is not a party, unless compelled by court process, nor shall such persons give sworn<br />

CM @ Risk Agreement R0787918R1 Page 77 of 85