DIVISION 1 SPECIFICATIONS<br />

SECTION 01315 PROGRESS SCHEDULES (COMPUTERIZED CPM)<br />

Exhibit 2<br />

Page 268 of 379<br />

9. If the CONTRACTOR’s monthly Updated Progress Schedule reflects, or<br />

the CPM determines, that the CONTRACTOR is at least fifteen (15) or<br />

more calendar days behind the recognized Baseline Schedule for the<br />

Project Milestones or an item of work on which is on the critical path, then<br />

the CONTRACTOR shall submit with the monthly Updated Progress<br />

Schedule, or within seven (7) days of a written request from the CPM, his<br />

proposed plan for bringing the work back on schedule <strong>and</strong> completing the<br />

work by the contract completion date(s).<br />

10. If the monthly Updated Progress Schedule is rejected, the<br />

CONTRACTOR shall resubmit the update for approval within seven (7)<br />

calendar days. If the resubmittal of the schedule does not occur within<br />

seven (7) calendar days, the withholding of progress payments may<br />

occur, per paragraph G. 9. of this specification section.<br />

1.07 REVISIONS TO BASELINE SCHEDULE<br />

A. Updating the Schedule to reflect actual progress to date shall not be considered a<br />

revision of the Schedule.<br />

B. With the CA’s approval, the CONTRACTOR shall revise the Baseline Schedule when<br />

one or more of the following conditions occur:<br />

1. When a change or delay significantly affects any specified intermediate<br />

milestone or completion dates.<br />

2. When the CONTRACTOR elects to change any sequence of activities<br />

affecting the critical path or to significantly change the previously<br />

approved work plan.<br />

3. When, in the opinion of the CPM, the status of the work is such that the<br />

Baseline Schedule <strong>and</strong> supporting analysis no longer accurately<br />

represents the Work for planning <strong>and</strong> progress evaluation purposes;<br />

requires CA approval.<br />

4. Upon issuance of additional Notices to Proceed.<br />

5. Upon subcontract award.<br />

6. When CONTRACTOR receives BCAD Project Manager approval to<br />

change the logic per section 1.10 of this section (01315).<br />

C. Submit any revised Baseline Schedule in the same form <strong>and</strong> detail as the<br />

Preliminary Baseline Schedule submittal requirements.<br />

D. Changes in the Baseline Schedule to reflect revisions in the method of operating <strong>and</strong><br />

scheduling of work shall be made by notifying the CPM in writing, stating reason for<br />

the proposed revision(s).<br />

E. Reasonable requests for revisions from the CPM shall be implemented by the<br />

CONTRACTOR.<br />

F. Revisions to the Baseline Schedule requested by the CPM will require written<br />

response from the CONTRACTOR within fourteen (14) calendar days of the<br />

requested revision.<br />

Section 01315 Progress Schedule (Computerized CPM) Page 63