DIVISION 1 SPECIFICATIONS<br />

SECTION 01315 PROGRESS SCHEDULES (COMPUTERIZED CPM)<br />

Exhibit 2<br />

Page 269 of 379<br />

G. Change Orders:<br />

1. Requests for change orders shall include statements as to the effect of<br />

the requested change on the CONTRACTOR’s schedule <strong>and</strong> costs. In<br />

cases where the requested change has no impact on cost or schedule,<br />

statements to that effect shall still be included.<br />

2. As a minimum, a requested change order or time extension which affects<br />

the schedule will include a fragnet showing the schedule network logic<br />

<strong>and</strong> durations of any <strong>and</strong> all added or changed activities to the schedule.<br />

This fragnet will only show the changes <strong>and</strong> / or added activities made<br />

necessary by the requested change order. The fragnet must be approved<br />

before incorporation into the CONTRACTOR’s current accepted Updated<br />

Progress Schedule or Baseline Schedule.<br />

3. Incorporation of approved change orders shall reflect impacts on the<br />

current Updated Progress Schedule <strong>and</strong> Baseline Schedule.<br />

1.08 ADJUSTMENT OF TIME FOR COMPLETION<br />

A. Time for Completion will be adjusted only in accordance with this Clause <strong>and</strong> the<br />

Agreement.<br />

B. Any request for adjustment of time for completion because of changes or alleged<br />

delays shall be accompanied by a complete Time Impact Analysis which shall be<br />

submitted for approval within seven (7) calendar days after initial notice of delay.<br />

C. Each Time Impact Analysis shall provide information justifying the request <strong>and</strong><br />

stating extent of adjustment requested for each specific change or alleged delay.<br />

Each Analysis shall be on form <strong>and</strong> content acceptable to the CPM, <strong>and</strong> shall<br />

include, but not be limited to, the general information set forth in this section<br />

appropriate to the type of request (change or alleged delay) plus the following:<br />

1. Fragnet schedule illustrating how the change, or the alleged delay, is<br />

proposed to be incorporated into the current Updated Progress Schedule.<br />

2. Identification of activities in current Updated Progress Schedule which are<br />

proposed to be amended due to change or alleged delay, together with<br />

engineering estimates <strong>and</strong> other appropriate data justifying proposal.<br />

3. Supporting documentation in the form of technical documents,<br />

correspondence, daily reports, directives, <strong>and</strong> / or other forms of<br />

documentation relevant to the change or alleged delay.<br />

D. Seasonal weather conditions shall be considered <strong>and</strong> included in the planning<br />

<strong>and</strong> scheduling of all work influenced by high or low ambient temperatures, wind,<br />

precipitation <strong>and</strong> / or saturated soil, to ensure completion of all Work within the<br />

Contract Time. Seasonal weather conditions shall be determined by an<br />

assessment of mean historical climatic conditions based upon the preceding ten<br />

(10) year records published for the locality by the U.S. Weather Bureau Service.<br />

Section 01315 Progress Schedule (Computerized CPM) Page 64