Exhibit 2<br />

Page 69 of 379<br />

Terminal 4 Gate Replacement – Western Expansion<br />

31of such delay, neglect or default, specifying the same. If CA or CPM (where applicable),<br />

within a period of ten (10) calendar days after such notice shall not remedy the delay, neglect,<br />

or default upon which the notice is based, then CONTRACTOR may stop work or terminate this<br />

Agreement <strong>and</strong> recover from <strong>COUNTY</strong> payment for all work executed <strong>and</strong> reasonable expenses<br />

sustained therein plus reasonable termination expenses.<br />

ARTICLE 30 - RESOLUTION OF DISPUTES<br />

30.1 Questions, claims, difficulties <strong>and</strong> disputes of whatever nature which may arise relative<br />

to the technical interpretation of the Contract Documents <strong>and</strong> fulfillment of this<br />

Agreement as to the character, quality, amount <strong>and</strong> value of any work done <strong>and</strong><br />

materials furnished, or proposed to be done or furnished under or, by reason of, the<br />

Contract Documents which cannot be resolved by mutual agreement of PMO, CPM <strong>and</strong><br />

CONTRACTOR shall be submitted to CA in writing for resolution. When either party has<br />

determined that a disputed question, claim, difficulty or dispute is at an impasse that<br />

party shall notify the other party in writing <strong>and</strong> submit the question, claim, difficulty or<br />

dispute to the CA for resolution. The parties may agree to a proposed resolution at any<br />

time without the involvement <strong>and</strong> determination of the Contract Administrator.<br />

30.2 CA shall notify PMO, CPM <strong>and</strong> CONTRACTOR in writing of CA’s decision within twentyone<br />

(21) calendar days from the date of the submission of the question, claim, difficulty<br />

or dispute, unless CA requires additional time to gather information or allow the parties<br />

to provide additional information. Contract Administrator’s estimates <strong>and</strong> decisions upon<br />

all questions, claims, difficulties <strong>and</strong> disputes shall be final <strong>and</strong> binding to the extent<br />

provided in Section 30.5.<br />

30.3 All non-technical administrative disputes (such as billing <strong>and</strong> payment <strong>and</strong> CBE reporting<br />

issues) shall be determined by the Contract Administrator.<br />

30.4 During the pendency of any dispute <strong>and</strong> after a determination thereof, CONTRACTOR,<br />

PMO, CPM, Consultant, <strong>and</strong> CA shall act in good faith to mitigate any potential damages<br />

including utilization of construction schedule changes <strong>and</strong> alternate means of<br />

construction. During the pendency of any dispute arising under this Agreement, other<br />

than termination herein, the CONTRACTOR shall proceed diligently with performance of<br />

this Agreement <strong>and</strong> the <strong>COUNTY</strong> shall continue to make payments for undisputed<br />

amounts in accordance with the Contract Documents.<br />

30.5 In the event the determination of a dispute by the CA under this Article is unacceptable<br />

to any of the parties hereto, the party objecting to the determination must notify the other<br />

party, the County Administrator or designee, in writing within ten (10) calendar days of<br />

receipt of the written determination. The notice must state the basis of the objection <strong>and</strong><br />

the objecting party’s proposed resolution. If notice is given by CONTRACTOR, it must be<br />

accompanied by a statement that any Contract Price or Contract Time adjustment<br />

claimed is the entire adjustment to which the CONTRACTOR has reason to believe it is<br />

entitled to as a result of the question, claim, difficulty or dispute. Resolution of such<br />

dispute shall be made by the County Administrator or designee. The County<br />

CM @ Risk Agreement R0787918R1 Page 68 of 85