DIVISION 1 SPECIFICATIONS - SECTION 01010 – SUMMARY OF WORK<br />

Exhibit 2<br />

Page 209 of 379<br />

D. Protection of Underground Facilities:<br />

The location of all underground facilities, including but not limited to gas, liquid<br />

petroleum, <strong>and</strong> FAA communications lines MUST be verified by the<br />

CONTRACTOR prior to starting any construction.<br />

1.03 LIMITS OF CONSTRUCTION AND CONTRACTOR USE OF PREMISES<br />

The work set forth in these contract documents includes the furnishing of all<br />

labor, materials, equipment, services <strong>and</strong> incidentals for construction.<br />

1.04 DESCRIPTION OF THE WORK<br />

The Work of the Project Terminal 4 Gate Replacement, repositioning/relocation<br />

of Certain Concourse H Gates, Western Expansion of Concourse H, a secure<br />

connector from Terminal 3 to the new Terminal 4, new office space for Broward<br />

County Aviation Department (BCAD) <strong>and</strong> related work at Fort Lauderdale -<br />

Hollywood International Airport as indicated in the Construction Drawings <strong>and</strong><br />

Specifications.<br />

1.05 PRODUCTS SUPPLIED BY OTHERS<br />

A. Items furnished by <strong>COUNTY</strong> for installation by <strong>COUNTY</strong>:<br />

The <strong>COUNTY</strong> may award various contracts for purchasing <strong>and</strong> installing<br />

specified materials. Material Lists from those purchase contracts are listed in the<br />

Contract Documents. The CONTRACTOR shall cooperate with the <strong>COUNTY</strong><br />

CONTRACTORS <strong>and</strong> provide access to the work areas as necessary.<br />

B. Items furnished by <strong>COUNTY</strong> for installation by CONTRACTOR:<br />

1.06 SCHEDULING<br />

The <strong>COUNTY</strong> may award various contracts for purchasing <strong>and</strong> installing<br />

specified materials. Material Lists from those purchase contracts are listed in the<br />

Contract Documents. The CONTRACTOR shall receive, inspect, unload<br />

specified materials from the transporter, transport to secure storage, <strong>and</strong> load<br />

<strong>and</strong> deliver the materials to the site for installation.<br />

The CONTRACTOR shall be responsible for the planning <strong>and</strong> scheduling, <strong>and</strong><br />

coordination of all Work performed under the Contract Documents, so that<br />

materials will arrive on schedule <strong>and</strong> installation will proceed without delay.<br />

Section 01010 Summary of Work Page 4