DIVISION 1 SPECIFICATIONS<br />

SECTION 01340 – SHOP DRAWINGS, PRODUCT DATA AND SAMPLES<br />

requirements of project closeout information, materials, tools, <strong>and</strong> similar<br />

items.<br />

6. General Distribution: Provide additional distribution of submittals to<br />

subcontractors, suppliers, fabricators, installers, governing authorities,<br />

<strong>and</strong> others as necessary for the proper performance of the Work. Include<br />

such additional copies in the submittals to the CONSULTANT where the<br />

submittals are required to receive “Action” marking before final<br />

distribution. Record distributions on transmittal forms.<br />

1.06 CONTRACTOR’ DUTIES<br />

A. Review submittals prior to transmittal; determine <strong>and</strong> verify field measurements,<br />

field construction criteria, manufacturer’s catalog numbers, <strong>and</strong> conformance of<br />

submittal with requirements of Contract Documents.<br />

B. Coordinate submittals with requirements of Work <strong>and</strong> of Contract Documents.<br />

C. Submittals or Accompanying Transmittal Letter Shall Contain:<br />

Exhibit 2<br />

Page 281 of 379<br />

1. Date of submission <strong>and</strong> dates of previous submissions when applicable.<br />

2. Project title <strong>and</strong> number.<br />

3. Contract identification.<br />

4. Names of subcontractor, supplier, <strong>and</strong> manufacturer.<br />

5. Identification of product with Specification Section number.<br />

6. Field dimensions, clearly identified as such.<br />

7. Relation to adjacent or critical features of work of materials.<br />

8. Applicable st<strong>and</strong>ards, such as, ASTM or Federal Specification numbers.<br />

9. Identification of revisions on resubmittal.<br />

10. Additional information required by Contract Documents.<br />

11. CONTRACTOR executed review <strong>and</strong> approval marking or stamp.<br />

12. Blank space for CPM’s <strong>and</strong> CONSULTANT’s action marking or stamp.<br />

13. CONTRACTOR to carefully check all submittals <strong>and</strong> be responsible for<br />

dimensions, quantity etc. necessary to make a complete project in<br />

compliance with plans <strong>and</strong> specifications.<br />

D. Clearly identify on submittals, or in writing at time of submission, deviations in<br />

submittals from requirements of Contract Documents. CONTRACTOR’s<br />

responsibility for deviations in submittals from requirements of Contract<br />

Documents is not relieved by CPM <strong>and</strong> CONSULTANT’s review of submittals<br />

unless CONSULTANT furnishes written recommendation of acceptance of<br />

specific deviations to the CPM <strong>and</strong> the CPM provides written acceptance to<br />

CONTRACTOR.<br />

E. Apply CONTRACTOR’s mark or stamp, sign, <strong>and</strong> date, Signature of<br />

CONTRACTOR’s authorized person certified verification of products, verification<br />

of field measurements <strong>and</strong> field construction criteria, <strong>and</strong> coordination of<br />

information within submittal with requirements of work <strong>and</strong> of Contract<br />

Documents. Submittals without CONTRACTOR’s executed mark or stamp <strong>and</strong><br />

signature will be returned without disposition.<br />

Section 01340 Shop Drawings, Product Data <strong>and</strong> Samples Page 76