DIVISION 1 SPECIFICATIONS<br />

SECTION 01315 PROGRESS SCHEDULES (COMPUTERIZED CPM)<br />

Order. Upon receipt of an approved Change Order modifying the contract<br />

completion date, the CONTRACTOR shall reissue a new Baseline schedule,<br />

without status data, to serve as a modified baseline schedule.<br />

1.10 RESPONSIBILITY FOR COMPLETION<br />

A. The CONTRACTOR shall furnish sufficient forces, offices, facilities <strong>and</strong><br />

equipment, <strong>and</strong> shall work such hours including night shift <strong>and</strong> overtime<br />

operations, as necessary to ensure the prosecution of the Work in accordance<br />

with the current monthly Updated Progress Schedule. If, in the opinion of the<br />

CPM, the CONTRACTOR, due to its own action, falls behind in meeting the<br />

Baseline Schedule as presented in the current monthly Updated Progress<br />

Schedule, the CONTRACTOR shall take such steps as may be necessary to<br />

improve its progress, <strong>and</strong> the CPM through the BCAD Project Manager may<br />

require the CONTRACTOR to increase the hours of work, the number of shifts,<br />

the amount of supervision, overtime operations <strong>and</strong> / or the amount of<br />

construction equipment without additional cost to the County. The provisions of<br />

this section shall not be construed as prohibiting work on Saturdays, Sundays,<br />

<strong>and</strong> holidays, if the CONTRACTOR so elects <strong>and</strong> gives reasonable notice to the<br />

CPM.<br />

B. The CONTRACTOR may improve its progress by performing sequential activities<br />

concurrently, by performing activities more quickly than planned, or by revising<br />

schedule logic to reflect a work around sequence. The CONTRACTOR may<br />

make minor logic changes, which are required to reflect actual work as it is<br />

performed, pertaining to out-of-sequence work. The minor logic changes shall be<br />

included in the monthly Updated Progress Schedule report in a format similar to<br />

that provided by Digger 2.0 software or Schedule Analyzer Pro software.<br />

1.11 PARTIAL PAYMENTS<br />

Exhibit 2<br />

Page 271 of 379<br />

A. Requests for partial payment must be accompanied by the Updated Progress<br />

Schedule. Requests for payment will not be processed unless properly<br />

submitted as specified.<br />

PART 2 - PRODUCTS<br />

PART 3 - EXECUTION<br />

(Not Used)<br />

(Not Used)<br />

END OF SECTION 01315 - PROGRESS SCHEDULES (COMPUTERIZED CPM)<br />