DIVISION 1 SPECIFICATIONS<br />

SECTION 01255 CPEAM PROCEDURES<br />

Exhibit 2<br />

Page 244 of 379<br />

(including final CPEAM documents necessary for the calculation of<br />

shared savings). Contractor shall utilize Contract Administrator's<br />

st<strong>and</strong>ardized CPEAM forms. Customization of the Contract<br />

Administrator's st<strong>and</strong>ardized CPEAM forms may be allowed with the<br />

Contract Administrator's prior written authorization if necessary to<br />

accurately portray unique project conditions.<br />

2. When CPM, Consultant <strong>and</strong> Contract Administrator's staff have reviewed<br />

<strong>and</strong> conceptually approved the Contractor's proposal (Document<br />

01260A), the Contractor shall prepare a draft Contract Price Element<br />

Adjustment Memor<strong>and</strong>um (CPEAM) for the Contract Administrator's<br />

consideration.<br />

3. Contractor shall submit draft CPEAM's to the CPM <strong>and</strong> Consultant for<br />

review <strong>and</strong> signature. Once signed by CPM, the CONTRACTOR shall<br />

convene a meeting with the Contract Administrator to review the draft<br />

CPEAM. That meeting shall include the Consultant, Contractor, Contract<br />

Administrator <strong>and</strong> CPM, the County's Project Manager <strong>and</strong> members of<br />

the Contract Administrator's administrative staff. Contractor shall provide<br />

final CPEAM's reflecting the outcome of the review <strong>and</strong> approval meeting<br />

for the Contract Administrator’s signature with appropriate backup to<br />

illustrate the transactions delineated on the CPEAM.<br />

4. Changes to the Contract Price Elements or CPEAM's which are critically<br />

needed to facilitate the continuing progress of the Work should be so<br />

identified on the submitted Document 01260B, Change Order Request<br />

(Proposal). The CA may issue Document 01260E: Construction Change<br />

Directive, directing the CONTRACTOR to proceed with Work related to a<br />

critically required CPEAM.<br />

1.04 EXECUTION OF CPEAM's<br />

CONTRACTOR shall prepare CPEAM forms <strong>and</strong> obtain Contract Administrator's<br />

signature through the CPM. CPEAM's shall not be considered in effect until<br />

signed by the Contract Administrator.<br />

1.05 CORRELATION OF CONTRACTOR SUBMITTALS<br />

A. Promptly revise Schedule of Values <strong>and</strong> Application for Payment forms to record<br />

each authorized CPEAM.<br />

B. Promptly revise progress schedules to reflect any change in Contract Time,<br />

revise subschedules to adjust times for other items of work affected by the<br />

CPEAM, <strong>and</strong> resubmit.<br />

C. Promptly enter changes in Project As-Built Documents.<br />