DIVISION 1 SPECIFICATIONS<br />

SECTION 01540 CONSTRUCTION SAFETY PLAN AND SECURITY REQUIREMENTS<br />

M. LIMITATION OF OPERATIONS:<br />

1. When the Work requires the CONTRACTOR to operate on or adjacent to<br />

the public area of the Terminal Building the operation shall be coordinated<br />

with BCAD through the CPM at least 48 hours prior to commencement of<br />

the Work. At no time shall the CONTRACTOR close a Public Area until<br />

authorization to do so has been granted by the CPM.<br />

2. When the Contract Work requires the CONTRACTOR to operate on or<br />

adjacent to the apron or taxiway AOA, the operation shall be coordinated<br />

with BCAD-Operations through the CPM, at least 48-hours prior to<br />

commencement of the Work. At no time shall the CONTRACTOR close<br />

an Air Operation Area (AOA) until authorization to do so has been<br />

granted by the CPM <strong>and</strong> until temporary marking <strong>and</strong> associated lighting<br />

is provided <strong>and</strong> in place as specified in FAA Advisory Circular 150/5340-<br />

1E, “Marking of Pave Area on Airports” <strong>and</strong>/or the Drawings <strong>and</strong><br />

Specifications.<br />

3. The CONTRACTOR shall be responsible for controlling his operations<br />

<strong>and</strong> those of his subcontractors so as to provide for the free <strong>and</strong><br />

unobstructed movement of all passengers <strong>and</strong> private vehicles in the<br />

Airport.<br />

4. The CONTRACTOR shall be responsible for controlling his operations<br />

<strong>and</strong> those of his subcontractors so as to provide for the free <strong>and</strong><br />

unobstructed movement of aircraft in the apron <strong>and</strong> taxiway areas of the<br />

Airport Operations Area (AOA).<br />

5. When the Contract Work requires the CONTRACTOR to work with an Air<br />

Operations Area (AOA) of the Airport on an intermittent basis (intermittent<br />

opening <strong>and</strong> closing of the AOA), the CONTRACTOR shall maintain<br />

constant communication; immediately obey all instructions to resume<br />

Work in such AOA. Failure to maintain the specified communications or<br />

to obey instructions shall be cause for suspension of the<br />

CONTRACTOR’s operations in the AOA until the satisfactory conditions<br />

are provided.<br />

N. OBSTRUCTIONS TO NAVIGATION:<br />

1. Penetrations of the imaginary surfaces defined in FAR Part 77 shall not<br />

be permitted without advance notification of <strong>and</strong> approval by BCAD-<br />

Operations <strong>and</strong> the FAA Tower Chief. It may be necessary to file Form<br />

7460-1 with the FAA to obtain approval prior to operation of exceptionally<br />

tall equipment. This includes any penetrations whatsoever by the<br />

CONTRACTOR, including, but not limited to, vehicles, cranes, other<br />

construction equipment, structures, stockpiled materials, excavated earth,<br />

etc.<br />

2. When penetrations are unavoidable they shall be brought to the attention<br />

of BCAD-Operations, the CPM <strong>and</strong> the FAA as far in advance as is<br />

practical to allow Notices to Airmen (NOTAMS) to be prepared <strong>and</strong><br />

distributed to appropriate FAA divisions for publication <strong>and</strong> dissemination.<br />

3. Appropriate sketches shall be prepared by the CONTRACTOR with<br />

precise locations shown on the Airport Layout Plan along with elevations<br />

Section 01540 Construction Plan <strong>and</strong> Safety Requirements Page 103