DIVISION 1 SPECIFICATIONS<br />

SECTION 01315 PROGRESS SCHEDULES (COMPUTERIZED CPM)<br />

development <strong>and</strong> acceptance of the Baseline Schedule. The Preliminary<br />

Baseline Schedule submittal shall be based on the joint review meeting<br />

<strong>between</strong> the CONTRACTOR, CPM <strong>and</strong> Consultant. The Preliminary<br />

Baseline Cost Loaded schedule shall be submitted no later than the<br />

submission of the first pencil copy of the Application for Payment for the<br />

sub-contracted work.<br />

2. The Preliminary Baseline Schedule must show in detail the activities to be<br />

accomplished through the first phase of Pre-Construction Services <strong>and</strong><br />

Early Investigation Work, as well as an overall preliminary schedule<br />

indicating a comprehensive overview of the Work including an activity line<br />

for each major element of the work segments.<br />

3. Additional Preliminary Baseline Schedules may be required to detail the<br />

activities for continued phases of Pre-Construction Services <strong>and</strong> Early<br />

Construction Work, as required by the CPM.<br />

C. SCHEDULE DEVELOPMENT<br />

1. Within ten (10) calendar days after date of Early Construction Work<br />

Notice-to-Proceed, CONTRACTOR shall revise the Preliminary Schedule<br />

for approval by the CPM. This revised schedule must include detailed<br />

Early Work activities, <strong>and</strong> should further detail activities of the<br />

comprehensive overview, including development <strong>and</strong> approval of the<br />

GMP. This revised Preliminary Baseline Schedule shall not change the<br />

date of Final Completion except as otherwise provided by approved<br />

Change Order.<br />

2. Within ten (10) calendar days of the GMP Notice to Proceed, the<br />

CONTRACTOR shall revise the Preliminary Baseline Schedule for<br />

approval by the CPM, This revised schedule shall become the Baseline<br />

Schedule used to monitor the GMP work. The CONTRACTOR shall<br />

revise the Baseline Schedule for each subcontract awarded, but not less<br />

than weekly, <strong>and</strong> include the provisions for a cost loaded <strong>and</strong> resource<br />

loaded schedule. The Final Completion date cannot be changed by any<br />

revision incorporating subcontract awards, except as otherwise provided<br />

by approved Change Order.<br />

3. Construct the Baseline Schedule to indicate a logical sequence of work<br />

activities <strong>and</strong> durations. Incorporate major restrictions from the<br />

availability <strong>and</strong> use of manpower, material, <strong>and</strong> equipment. Utilize the<br />

Baseline Schedule in planning, scheduling, coordinating <strong>and</strong> performing<br />

the Work under this CONTRACT (including all activities of subcontractors,<br />

equipment vendors, suppliers, <strong>and</strong> relevant third parties – BCAD, FPL,<br />

CPM, related / adjacent projects, or others).<br />

4. In the Baseline Schedule shall provide sufficient detail <strong>and</strong> clarity of form<br />

<strong>and</strong> technique so that the Work can be properly monitored by the CPM.<br />

The Baseline Schedule shall comply with the various limits imposed by<br />

the Scope of Work <strong>and</strong> by any contractually specified intermediate<br />

milestone dates <strong>and</strong> completion dates. The degree of detail shall be to<br />

the satisfaction of the CPM <strong>and</strong> shall be sufficient to identify:<br />

a. Structural breakdown of the project<br />

b. Types of work being performed<br />

Exhibit 2<br />

Page 263 of 379<br />

Section 01315 Progress Schedule (Computerized CPM) Page 58