DIVISION 1 SPECIFICATIONS<br />

SECTION 01561 CONSTRUCTION CLEANING<br />

Exhibit 2<br />

Page 320 of 379<br />

PART 1 - GENERAL<br />

1.01 REQUIREMENTS INCLUDED<br />

A. CONTRACTOR shall enforce daily cleaning during progress of Work <strong>and</strong> enforce<br />

final cleanup prior to Substantial Completion.<br />

B. Hazards Control:<br />

1. Store volatile wastes in covered metal containers.<br />

2. Remove containers from premises daily.<br />

3. Prevent accumulation of wastes that create hazardous conditions.<br />

4. Provide adequate ventilation during use of volatile or noxious substances.<br />

C. Conduct cleaning <strong>and</strong> disposal operations to comply with local ordinances <strong>and</strong><br />

anti-pollution laws:<br />

PART 2 - PRODUCTS<br />

2.01 MATERIALS<br />

1. Do not burn or bury rubbish or waste materials on Project Site.<br />

2. Do not dispose of volatile wastes, such as mineral spirits, oil, or paint<br />

thinner in storm or sanitary drains.<br />

3. Transport waste materials <strong>and</strong> debris across airport property in covered<br />

trucks.<br />

A. Use cleaning materials recommended by manufacturer or surface to be cleaned<br />

which will not create hazards to health or property <strong>and</strong> which will not damage<br />

surfaces.<br />

B. See Technical Specifications for specific products.<br />

PART 3 - EXECUTION<br />

3.01 CLEANING DURING CONSTRUCTION<br />

A. Enforce cleaning to keep building, grounds, <strong>and</strong> public properties free of<br />

accumulation of waste materials, rubbish, <strong>and</strong> windblown debris resulting from<br />

construction operations.<br />

B. Have protective covering applied on newly installed Work where reasonable<br />

required to ensure freedom from damage or deterioration at time of Substantial<br />

Completion. Enforce cleaning <strong>and</strong> maintenance on other newly installed Work as<br />

frequently as necessary through remainder of construction period.<br />

C. Have operable components adjusted <strong>and</strong> lubricated to ensure operability without<br />

damaging effects.<br />

Section 01561 Construction Cleaning Page 115