DIVISION 1 SPECIFICATIONS<br />

SECTION 01255 CPEAM PROCEDURES<br />

Exhibit 2<br />

Page 231 of 379<br />

PART 1 - GENERAL<br />

1.01 AIRPORT OPERATIONS<br />

A. Airport operations shall be maintained throughout this Contract. The<br />

CONTRACTOR shall in no way curtail or h<strong>and</strong>icap normal operational<br />

characteristics of the airport facility except as specifically indicated <strong>and</strong> specified<br />

in the Contract Documents.<br />

1.02 PERMITS, LICENSES AND TAXES<br />

A. CONTRACTOR shall secure all permits, arrange for all inspections <strong>and</strong> similar<br />

procedural items as required by the code enforcement authorities having<br />

jurisdiction.<br />

B. The CONTRACTOR shall procure all necessary <strong>and</strong> required licenses in<br />

accordance with the General Conditions provisions of THE CM-AT-RISK<br />

CONTRACT (CMR).<br />

1.03 VERIFICATION OF EXISTING CONDITIONS<br />

A. The CONTRACTOR shall familiarize himself as to the existing conditions.<br />

Should the CONTRACTOR discover any inaccuracies, errors, or omissions<br />

<strong>between</strong> the actual existing conditions <strong>and</strong> the Contract Documents, he shall<br />

notify the CPM in writing within three (3) calendar days.<br />

1.04 MAINTENANCE OF TRAFFIC<br />

A. It is the explicit intention of the Contract that the safety of aircraft, the public, as<br />

well as the CONTRACTOR’s equipment <strong>and</strong> personnel, is the most important<br />

consideration. It is understood <strong>and</strong> agreed that the CONTRACTOR shall provide<br />

for the free <strong>and</strong> unobstructed movement of aircraft in the air operations areas of<br />

the airport with respect to his/her own operations <strong>and</strong> the operations of all his/her<br />

subcontractors as specified in Section 01540 - CONSTRUCTION SAFETY PLAN<br />

AND SECURITY REQUIREMENTS. It is further understood <strong>and</strong> agreed that the<br />

CONTRACTOR shall furnish <strong>and</strong> install for the uninterrupted operation of visual<br />

<strong>and</strong> electronic signals (including power supplies thereto) used in the guidance of<br />

aircraft.<br />

B. The cost of maintaining the vehicular traffic specified in the Contract Documents<br />

shall be included in CONTRACTOR’s Construction General Conditions.<br />

Section 01255 CPEAM Procedures Page 26