Exhibit 2<br />

Page 33 of 379<br />

Terminal 4 Gate Replacement – Western Expansion<br />

Project except with the prior written consent of <strong>COUNTY</strong>. The Cost of the Work shall<br />

include only those items set forth in this Section 8.4 <strong>and</strong> shall not include any items<br />

listed in Section 8.5. Cost of the Work shall be determined as follows:<br />

8.4.1 Subcontractor Costs shall be:<br />

8.4.1.1 The CONTRACTOR’s Direct Construction Cost, as generally described on<br />

Exhibit 1, attached hereto, to be 100% performed by Subcontractors selected<br />

in accordance with Article 11, herein. Where the work is covered by unit prices<br />

contained in the Contract Documents or an applicable subcontract, the cost of<br />

the Work shall be determined by application of unit prices to the quantities of<br />

items involved.<br />

8.4.1.2 Where Subcontractor is owned by, or an affiliate of the CONTRACTOR or work<br />

is to be “self performed” by CONTRACTOR, no overhead <strong>and</strong> profit shall be<br />

allowed.<br />

8.4.1.3 If the subcontract provides that the Subcontractor is to be paid on the basis of<br />

Cost of the Work plus a fee, the Subcontractor’s Cost of the Work shall be<br />

determined in the same manner as CONTRACTOR’s Cost of the Work.<br />

8.4.2 CONTRACTOR’s Labor Costs: Payroll costs for employees in the direct employ of<br />

CONTRACTOR in the performance of the work described in the Contract Documents<br />

shall be limited to salaries plus labor burden as set forth in the schedule of job<br />

classifications agreed upon by <strong>COUNTY</strong> <strong>and</strong> CONTRACTOR in Exhibit 3<br />

(CONTRACTOR’s Management Services), <strong>and</strong> other non skilled labor costs which<br />

have the prior approval of the CA, subject to audit by <strong>COUNTY</strong>. Payroll costs for<br />

employees not employed full time on the work covered by the Agreement shall be<br />

apportioned on the basis of the time the employees spent on the work. Payroll costs<br />

shall be limited to salaries <strong>and</strong> wages plus the labor burden which includes social<br />

security contributions, unemployment, excise <strong>and</strong> payroll taxes, workers<br />

compensation, health insurance, sick leave, vacation, <strong>and</strong> holiday pay applicable<br />

thereto, only.<br />

8.4.3 Materials <strong>and</strong> Equipment: Cost of all necessary materials <strong>and</strong> equipment furnished<br />

<strong>and</strong> incorporated in the Work, including costs of transportation <strong>and</strong> storage thereof,<br />

<strong>and</strong> manufacturers’ field services required in connection therewith, adjusted in<br />

accordance with Article 10, Discounts, Rebates <strong>and</strong> Refunds; rentals of all<br />

construction equipment <strong>and</strong> machinery <strong>and</strong> the parts thereof, including all operating<br />

<strong>and</strong> maintenance costs, costs of transportation, loading, unloading, installation,<br />

dismantling <strong>and</strong> removal thereof, whether rented from CONTRACTOR or others. The<br />

rental of any such equipment, machinery or parts shall cease when the use thereof is<br />

no longer necessary for the Work.<br />

8.4.4 Miscellaneous costs:<br />

8.4.4.1 The cost, as documented by the CONTRACTOR’s detailed receipts, of<br />

telephone, telegrams, postage, photographs, blueprints, office supplies, first<br />

CM @ Risk Agreement R0787918R1 Page 32 of 85