DIVISION 1 SPECIFICATIONS<br />

SECTION 01040 PROJECT COORDINATION<br />

Exhibit 2<br />

Page 215 of 379<br />

PART 1 - GENERAL<br />

1.01 DESCRIPTION<br />

A. Minimum administration <strong>and</strong> supervisory requirements necessary for<br />

coordination of Work on the Project include but are not necessarily limited to the<br />

following:<br />

1. Pre-Construction Conference<br />

2. Coordination <strong>and</strong> Progress Meetings<br />

3. Administration <strong>and</strong> Supervisory personnel<br />

4. Special Reports<br />

5. Communications<br />

6. Daily Reports<br />

7. Record Drawings (As-Builts)<br />

8. Pre-Installation<br />

1.02 PRECONSTRUCTION CONFERENCE<br />

A. Before beginning Early Construction or GMP Work at the Site, the<br />

CONTRACTOR shall attend a preconstruction conference <strong>and</strong> bring with him the<br />

Project Management Team employed for this Project. In the event a Team<br />

member is unable to attend the CONTRACTOR shall bring with him a Letter of<br />

Introduction in which he advises the full names <strong>and</strong> duties of the Team<br />

member(s) <strong>and</strong> states that they are assigned to the Project <strong>and</strong> will be in full<br />

responsible charge. This conference will be called by the CPM who will arrange<br />

for the CONSULTANT <strong>and</strong> other interested parties to be present. The<br />

CONTRACTOR shall also notify his major subcontractors <strong>and</strong> suppliers of this<br />

meeting if their attendance is required. At this time, all parties will discuss the<br />

Project under Contract <strong>and</strong> prepare a program of procedure in keeping with<br />

requirements of the Contract Documents. The CONTRACTOR’s Project<br />

Management Team will henceforth make every effort to expeditiously coordinate<br />

all phases of the Work, including the required reporting procedure, to obtain the<br />

end result within the full purpose <strong>and</strong> intent of the Contract Documents for this<br />

Project.<br />

1.03 COORDINATION AND PROGRESS MEETINGS<br />

A. The CPM will prepare a written memor<strong>and</strong>um on required coordination activities.<br />

Included will be such items as required notices, reports, <strong>and</strong> attendance at<br />

meetings. This memor<strong>and</strong>um will be distributed to each entity performing<br />

construction at the Project Site.<br />

Section 01040 Project Coordination Page 10