Exhibit 2<br />

Page 25 of 379<br />

Terminal 4 Gate Replacement – Western Expansion<br />

calendar days of the Substantial Completion date, CONTRACTOR shall pay the<br />

<strong>COUNTY</strong> the sum of five hundred dollars ($500.00) for each calendar day. These<br />

amounts are not penalties but are liquidated damages paid to <strong>COUNTY</strong> for its<br />

inability to obtain full beneficial occupancy of the Project. Liquidated damages are<br />

hereby fixed <strong>and</strong> agreed upon <strong>between</strong> the parties, recognizing the impossibility of<br />

precisely ascertaining the amount of damages that will be sustained by <strong>COUNTY</strong> as<br />

a consequence of such delay, <strong>and</strong> both parties desiring to obviate any questions of<br />

dispute concerning the amount of said damages <strong>and</strong> the cost <strong>and</strong> effect of the failure<br />

of CONTRACTOR to complete the Agreement on time.<br />

6.1.6 The CA is authorized to deduct liquidated damages from monies due to<br />

CONTRACTOR for the work under this Agreement or as much thereof as the CA<br />

may, at its sole option, deem just <strong>and</strong> reasonable.<br />

6.1.7 Extensions to the Contract Time for delays caused by the effects of extraordinary<br />

adverse weather shall be submitted as a request for change in Contract Time<br />

pursuant to Section 6.5. These time extensions are justified only when extraordinary<br />

adverse weather conditions or related adverse soil conditions prevent<br />

CONTRACTOR from productively performing critical path activities, identified on the<br />

accepted Baseline Schedule or updates, resulting in the CONTRACTOR being<br />

unable to work at least fifty (50%) of the normal workday on Critical Path activities for<br />

three or more consecutive days.<br />

6.2 The CA through the PMO <strong>and</strong> CPM may direct the CONTRACTOR to expedite the Work by<br />

whatever means the CONTRACTOR may use, including, without limitation, increasing<br />

staffing or working overtime to bring the Work back within the Baseline Schedule. If<br />

expediting the Work is required due to reasons within the control or responsibility of the<br />

CONTRACTOR, then the additional costs incurred shall be absorbed by the CONTRACTOR<br />

without issuing a CPEAM from the CONTRACTOR’s Contingency account. If the expediting<br />

of Work is required due to reasons outside the control or responsibility of the<br />

CONTRACTOR, then the additional costs incurred shall be the subject of an appropriate<br />

adjustment issued pursuant to Section 7.3 or Section 7.4, herein as applicable.<br />

6.3 Substantial Completion Date: When CONTRACTOR considers that the Work, or portion<br />

thereof designated by the CA pursuant to Section 6.4 herein, has reached Substantial<br />

Completion, CONTRACTOR shall so notify CA, PMO, CPM <strong>and</strong> Consultant in writing with a<br />

comprehensive list of items to be completed or corrected by CONTRACTOR. CPM <strong>and</strong><br />

Consultant shall then promptly in accordance with Division 1 Specifications make a<br />

preliminary inspection of the Work. When CPM, on the basis of the preliminary inspection,<br />

determines that the Work or designated portion thereof is substantially complete, PMO will<br />

notify the CA. CA shall then, with the PMO, CPM, Consultant <strong>and</strong> CONTRACTOR, perform<br />

the CA’s Substantial Completion Inspection. At the completion of the CA’s Substantial<br />

Completion Inspection, the CPM shall issue a Substantial Completion Inspection Report<br />

determining whether Substantial Completion has been achieved; such report shall include a<br />

Substantial Completion Punch List.<br />

6.3.1 When the CA’s Substantial Completion Inspection has determined that Substantial<br />

Completion of the Work, or a portion thereof, has been achieved, the CPM shall<br />

prepare a Certificate of Substantial Completion in the form attached hereto in the<br />

CM @ Risk Agreement R0787918R1 Page 24 of 85