DIVISION 1 SPECIFICATIONS - SECTION 01039 COORDINATION OF WORK<br />

Exhibit 2<br />

Page 212 of 379<br />

PART 1 - GENERAL<br />

1.01 COORDINATION OF WORK<br />

A. All areas of Project site will remain in operation during the course of construction.<br />

Coordination of access <strong>and</strong> scheduling of work in Customs <strong>and</strong> Border Protection<br />

(CBP), baggage, airside <strong>and</strong> passenger areas shall be identified <strong>and</strong> reviewed on<br />

a daily basis with CPM.<br />

B. Coordinate scheduling, submittals, <strong>and</strong> Work of the various Sections of<br />

specifications to assure efficient <strong>and</strong> orderly sequence <strong>and</strong> installation of<br />

interdependent construction elements.<br />

C. Verify that the utility requirement characteristics of operating equipment are<br />

compatible with building utilities. Coordinate work of various Sections having<br />

interdependent responsibilities for installing, connecting to, <strong>and</strong> placing in<br />

service, such equipment.<br />

D. Coordinate space requirements <strong>and</strong> installation of mechanical <strong>and</strong> electrical<br />

work, which are indicated diagrammatically on Drawings. Follow routing shown<br />

for pipes, ducts, <strong>and</strong> conduit, as closely as practicable; place runs parallel with<br />

line of building. Utilize spaces efficiently to maximize for other installations, for<br />

maintenance, <strong>and</strong> for repairs.<br />

E. In finished areas except as otherwise indicated, conceal pipes, ducts, <strong>and</strong> wiring<br />

within the construction. Coordinate locations of fixtures <strong>and</strong> outlets with finish<br />

elements.<br />

F. Coordinate completion <strong>and</strong> clean up of work of separate Sections in preparation<br />

for Substantial Completion.<br />

G. After <strong>COUNTY</strong> occupancy of premises, coordinate access to site for correction of<br />

defective work <strong>and</strong> work not in accordance with the Contract Documents, to<br />

minimize disruption of <strong>COUNTY</strong>’s activities.<br />

1.02 COORDINATION OF SPECIFICATIONS (Not Used)<br />

1.03 TIME FOR COMPLETION<br />

A. Time limits stated in the Contract Documents are the essence of the Contract.<br />

By executing the Agreement the CONTRACTOR confirms that the Time for<br />

Completion is a reasonable period for performing the work. The CONTRACTOR<br />

shall proceed expeditiously with adequate forces <strong>and</strong> shall achieve Substantial<br />

Completion within the time for completion.<br />

Section 01039 Coordination of Work Page 7