Terminal 4 Gate Replacement – Western Expansion<br />

9.5 CONTRACTOR’s Fixed Fee: The CONTRACTOR’s Fixed Fee is the stated amount to<br />

be paid to CONTRACTOR for the services rendered to <strong>COUNTY</strong> pursuant to Section<br />

9.1.D of this Agreement. The CONTRACTOR’s Fixed Fee shall not be increased by the<br />

distribution of the CONTRACTOR’s CONTINGENCY to other price elements within the<br />

GMP. The CA may consider increasing the Fixed Fee when the use of either the<br />

<strong>COUNTY</strong>’s Contingency or Document Completion Contingency increases the scope of<br />

the Work, through no fault of CONTRACTOR, for work unanticipated within the original<br />

GMP. All CA approved increases to the CONTRACTOR’s Fixed Fee shall be<br />

documented on the same Contract Price Element Adjustment Memor<strong>and</strong>um (CPEAM)<br />

prepared for the related transfer of <strong>COUNTY</strong>’s Contingency or Document Completion<br />

Contingency funds to the other price elements. Increases to the CONTRACTOR’s<br />

Fixed Fee shall be limited to 4%, as defined by Section 9.1.D.<br />

9.6 Document Completion Contingency: At the time of execution of this Agreement, the<br />

Contract Documents may not be complete. Therefore, it is understood that the sum<br />

shown in Section 9.1.E as the Document Completion Contingency is available to cover<br />

additional costs arising from building code interpretation disputes <strong>between</strong> the permitted<br />

set of drawings <strong>and</strong> Broward County Building Code Services or the Fire Marshal. At<br />

Final Completion of the Project, any remaining monies in the Document Completion<br />

Contingency shall vest in the <strong>COUNTY</strong>.<br />

9.7 CONTRACTOR’s Construction Contingency: An amount certain, set aside for the<br />

CONTRACTOR’s use against risks assumed in providing a GMP with uncertainties<br />

which are beyond the control of the CONTRACTOR. The contingency includes: bid<br />

results from vendors <strong>and</strong> suppliers due to changed market conditions, as measured<br />

against a relevant market index selected by the CA, <strong>and</strong> subject to the review <strong>and</strong><br />

approval of the CA, or other conditions which result in an increase in Direct Construction<br />

Cost through no fault of the CONTRACTOR. The CONTRACTOR will be required to<br />

furnish documentation, to the satisfaction of the CA, evidencing the expenditures<br />

charged to this Contingency as a precondition to release of any funds by the <strong>COUNTY</strong>.<br />

9.8 <strong>COUNTY</strong>’s Construction Contingency: These funds may be used to cover costs of<br />

additional elements of Work not included in the CONTRACTOR’s Construction Work,<br />

including but not limited to: <strong>COUNTY</strong> selected Subcontractors who are not the lowest<br />

responsive <strong>and</strong> responsible bidders for any portion of the work, <strong>COUNTY</strong> directed<br />

changes after permitting of the Work, differing site conditions, excusable delays as set<br />

forth in Section 7.6.2.2, post-hurricane Construction Directives, or errors <strong>and</strong> omissions<br />

in the Contract Documents. The CONTRACTOR shall not perform Work subject to the<br />

<strong>COUNTY</strong>’s Contingency Account without the Contract Administrator’s prior issuance of a<br />

CPEAM transferring such approved amounts to the CONTRACTOR’s Early Construction<br />

Work or other price element within the GMP.<br />

9.9 CONTRACTOR’s Early Construction Work: The costs negotiated <strong>between</strong> the <strong>COUNTY</strong><br />

<strong>and</strong> the CONTRACTOR for equipment, materials, labor, taxes <strong>and</strong> Subcontractors costs<br />

to complete certain portions of the Work which have been fully designed <strong>and</strong> permitted,<br />

prior to issuance of a building permit for GMP work.<br />

CM @ Risk Agreement R0787918R1 Page 40 of 85