DIVISION 1 SPECIFICATIONS<br />

SECTION 01255 CPEAM PROCEDURES<br />

Exhibit 2<br />

Page 240 of 379<br />

F. County’s St<strong>and</strong>ards of Construction:<br />

1. Hazardous Materials.<br />

a. ANY PRODUCT OR MATERIAL THAT CONTAINS ASBESTOS<br />

MATERIAL SHALL NOT BE PERMITTED ON THIS PROJECT.<br />

b. ANY LEAD-CONTAINING PAINT SHALL NOT BE USED ON<br />

THIS PROJECT.<br />

2. Building.<br />

a. Materials <strong>and</strong> finishes used in the Work shall have a fire rating at<br />

least equal to the rating required for the type space in which the<br />

Work is to be performed.<br />

b. No Work shall be performed which, when complete, will result in<br />

the degradation of the fire rating for the space.<br />

c. Any penetration of existing ceilings or walls which will break the<br />

fire rating of the ceiling or wall shall be patched with 5/8” Type X<br />

fire code sheetrock to the satisfaction of the CPM.<br />

d. Any ceiling access panel now existing shall remain in its present<br />

location <strong>and</strong> cannot be covered in a manner to prevent access.<br />

e. Any ceiling, other than CONTRACTOR’s own space, that must be<br />

accessed or crossed from above, will be done only with prior<br />

permission of the CPM.<br />

3. Electrical <strong>and</strong> Building Permits.<br />

a. All Broward County Permits shall be obtained <strong>and</strong> displayed at the<br />

Work site.<br />

b. All Work shall conform to all applicable codes.<br />

In addition, the County requires:<br />

1. All conductors (power, lighting, control or communication)<br />

shall be placed in conduit or routed by way of existing<br />

approved cable trays.<br />

2. ALL CONDUITS SHALL BE CONCEALED. (Special<br />

permission may be granted for exposed conduit in shop<br />

areas or some other places that are completely removed<br />

from office, commercial <strong>and</strong> public areas).<br />

3. Drawings show all Work to be performed. Drawings show<br />

new branch or feeder circuits <strong>and</strong> identify panel <strong>and</strong><br />

Section 01255 CPEAM Procedures Page 35