Exhibit 2<br />

Page 36 of 379<br />

Terminal 4 Gate Replacement – Western Expansion<br />

8.5.4 Other overhead, general expense costs or charges of any kind <strong>and</strong> the cost of<br />

any item not specifically <strong>and</strong> expressly included in Section 8.4.<br />

8.5.5 Costs in excess of the GMP.<br />

8.5.6 Entertainment <strong>and</strong> meal expenses, car allowances (except for vehicle(s) required<br />

to carry out the work stationed on-site with advance approval by the CA) <strong>and</strong><br />

charges of a personal nature.<br />

8.5.7 Bonuses, profit-sharing or other special labor charges not included in Section<br />

8.4.2, herein.<br />

8.5.8 Any outside legal or accounting fees incurred without prior written approval from<br />

the County Attorney, which approval is at the sole discretion of the County<br />

Attorney.<br />

8.6 Progress Payments:<br />

8.6.1 CONTRACTOR may make Application for Payment for Work completed during<br />

the Project at intervals of not more than once a month. CONTRACTOR shall,<br />

where the Project involves CBE Subcontractors, make application for payment<br />

for work completed by such Subcontractors during the Project at monthly<br />

intervals <strong>and</strong> shall pay its Subcontractors within thirty (30) calendar days<br />

following receipt of payment from the <strong>COUNTY</strong> for such subcontracted work.<br />

CONTRACTOR’s application shall show a complete breakdown of the Project<br />

components, the percentages completed <strong>and</strong> the amount due in proportion to the<br />

percentage of the Work completed or, as to General Conditions, at cost or, at the<br />

CA’s option, as a Negotiated Lump Sum payable in proportion to the percentage<br />

of the Work completed.<br />

8.6.2 Each application shall be accompanied by such supporting evidence as may be<br />

reasonably required by CPM or CA. Nevertheless, CONTRACTOR shall submit<br />

with each Application for Payment:<br />

an updated progress schedule acceptable to PMO, CPM <strong>and</strong> CA, as<br />

required by the Contract Documents;<br />

a monthly report as required by the Contract Documents;<br />

a Certification of Payments to Subcontractors (Form 00924);<br />

a release of liens from the CONTRACTOR relative to the work which is the<br />

subject of the previous pay Application;<br />

<br />

<br />

a completed Statement of Compliance, Form 1, attached hereto;<br />

Form 00924 shall be accompanied by a copy of the notification sent to each<br />

Subcontractor listed in item 2 of the form, explaining the good cause why<br />

payment has not been made. One original <strong>and</strong> four copies of each<br />

Application for Payment shall be submitted to CPM for certification <strong>and</strong><br />

distribution to the PMO <strong>and</strong> CA. <strong>COUNTY</strong> shall make payment to<br />

CONTRACTOR within thirty (30) calendar days after receipt of<br />

CONTRACTOR’s complete <strong>and</strong> accurate Application for Payment, as<br />

determined by the CA, <strong>and</strong> submission of an acceptable updated progress<br />

CM @ Risk Agreement R0787918R1 Page 35 of 85