DIVISION 1 SPECIFICATIONS<br />

SECTION 01255 CPEAM PROCEDURES<br />

Exhibit 2<br />

Page 243 of 379<br />

proposed change of Contract Price Element as an attachment to 01260B,<br />

Change Order Request (Proposal), then it is mutually agreed that the<br />

particular resulting CPEAM has no effect on contract time except as<br />

otherwise allowed elsewhere within the Contract Documents.<br />

4. When approved by the County, the sub-nets associated with that<br />

particular CPEAM shall be incorporated into the Baseline Schedule by the<br />

Contractor during the first update after such approval.<br />

1.03 CONTRACT PRICE ELEMENT CHANGE PROCEDURES<br />

A. Contract Change Orders:<br />

1. The Consultant or CPM may issue a Document 01260A: Proposal Request<br />

which may include a detailed description of a proposed change to the<br />

Contract Price Elements with supplementary or revised drawings <strong>and</strong><br />

specifications, a change in Contract Time for executing the change with a<br />

stipulation of any overtime work required <strong>and</strong> the period of time during which<br />

the requested price will be considered valid.<br />

a. Contractor shall prepare <strong>and</strong> submit an estimate within 14 days<br />

after receipt of the Proposal Request in the form of Document<br />

01260B, Change Order Request (Proposal) <strong>and</strong> supporting<br />

documentation as specified above <strong>and</strong> as might be required by<br />

the Consultant or the County.<br />

b. Such requests are informational <strong>and</strong> are not authorizations or<br />

instructions to execute the changes or stop the Work in progress.<br />

2. The Contractor may propose a change to the Contract Price Elements<br />

by submitting a request for change on Document 01260B, Change<br />

Order Request (Proposal) to the CPM or Consultant, by describing the<br />

proposed change <strong>and</strong> its full effect on the Work, with a statement<br />

describing the reason for the change, <strong>and</strong> the effect on the Contract<br />

Sum/Price <strong>and</strong> Contract Time with full documentation as required<br />

above <strong>and</strong> a statement describing the effect on Work by separate or<br />

other contractors.<br />

a. Provide additional detail regarding the proposed change as<br />

required by CPM, CA or Consultant including the cause <strong>and</strong> origin<br />

of the proposed change.<br />

b. Such proposals by the Contractor are informational <strong>and</strong> are not<br />

authorizations or instructions to execute the changes or slop the<br />

Work in progress.<br />

B. Contract Price Element Reallocation, Preparation of Proposed CPEAM's:<br />

1. Contract Administrator shall provide st<strong>and</strong>ardized CPEAM forms<br />

Section 01255 CPEAM Procedures Page 38