DIVISION 1 SPECIFICATIONS<br />

SECTION 01255 CPEAM PROCEDURES<br />

Exhibit 2<br />

Page 241 of 379<br />

G. Overhead Protection:<br />

breaker numbers where originating, size of conduit, size of<br />

wire, number of conductors <strong>and</strong> full load current.<br />

4. A manufacturers drawing shall be submitted on all new<br />

light fixtures showing type <strong>and</strong> size.<br />

1. No crane loads or other construction equipment shall cross over nonconstruction<br />

personnel, their travel ways to include, but not be limited to:<br />

walkways, roadways, or passenger transfer system tracks unless<br />

approved in writing by the CPM.<br />

2. The plan of operation of cranes <strong>and</strong> other hoisting equipment shall be<br />

established in writing by the CONTRACTOR. This plan of operation shall<br />

be subject to approval by the CPM.<br />

3. Specific areas affected by construction may require protective covering.<br />

These protective coverings, if required, shall be adequate to insure the<br />

protection of life <strong>and</strong> property <strong>and</strong> the continuous operation of the Airport.<br />

The layout <strong>and</strong> location of the protective systems shall be subject to<br />

review <strong>and</strong> rejection by the CPM. Structural integrity of protection<br />

systems shall be the responsibility of the CONTRACTOR.<br />

4. The use of helicopters to lift, place or otherwise maneuver equipment is<br />

expressly prohibited.<br />

1.09 CONSERVATION AND SALVAGE<br />

A. General.<br />

1. It is a requirement for supervision <strong>and</strong> administration of the Work that<br />

construction operations be carried out with the maximum possible<br />

consideration given to conservation of energy, water <strong>and</strong> materials. In<br />

addition, maximum consideration shall be given to salvaging materials<br />

<strong>and</strong> equipment involved in performance of the Work but not incorporated<br />

therein.<br />

2. Refer to other sections for required disposition of salvage materials,<br />

which are the County’s property.<br />

PART 2 - PRODUCTS<br />

PART 3 - EXECUTION<br />

(Not Used)<br />

(Not Used)<br />

END OF SECTION 01110 - AIRPORT PROJECT PROCEDURES<br />