DIVISION 1 SPECIFICATIONS<br />

SECTION 01540 CONSTRUCTION SAFETY PLAN AND SECURITY REQUIREMENTS<br />

representative.<br />

G. Open flame torch cutting or welding is prohibited unless adequate safety<br />

precautions have been taken <strong>and</strong> approved by the CPM. Use of explosively<br />

operated fastening devices within the confines of the Airport is strictly prohibited.<br />

H. The CONTRACTOR shall preserve <strong>and</strong>/or protect existing <strong>and</strong> new pavements<br />

plus other facilities from damage due to construction operations. Existing<br />

pavements <strong>and</strong> facilities that are damaged shall be replaced or reconstructed to<br />

original strength at the CONTRACTOR’s expense. The CONTRACTOR shall<br />

take immediate action to reconstruct any damaged area that is to remain in<br />

service. Unless indicated on the Drawings, existing pavements shall not be cut<br />

for the installation of any utilities. Jack <strong>and</strong> bore method shall be required.<br />

I. CONSTRUCTION AREA LIMITS:<br />

Exhibit 2<br />

Page 306 of 379<br />

1. FAA Advisory Circular 150/5370-2C, Appendix 1, prohibits construction<br />

activity within 125-feet of an active runway (open for aircraft use) edge or<br />

within the Obstacle Free Zone 150/5370-2C further restricts construction<br />

activity within 83.5-feet of the edge of the taxiway (48.5-feet of the<br />

shoulder edge) when the aircraft using the taxiway includes aircraft such<br />

as the B-747. The activity limits shall be adequately signed <strong>and</strong> marked<br />

by the CONTRACTOR to preclude violation of this restriction. The area<br />

shall be well identified by warning signs <strong>and</strong> lights at night. The<br />

CONTRACTOR shall install lighting, marking, barricades, signs <strong>and</strong> other<br />

measures to delineate closed <strong>and</strong> hazardous area during construction.<br />

The guidance <strong>and</strong> procedures provided by FAA Advisory Circular AC<br />

150/5340-1E, “Marking of Paved Areas on Airports”, shall be utilized as<br />

depicted on the Drawings. Barricades shall be weighted or otherwise<br />

secured to sufficiently prevent displacement by aircraft engine <strong>and</strong><br />

propeller blast <strong>and</strong> ambient winds. Steady burning red obstruction lights<br />

may be required in certain instances to supplement lighted barricades or<br />

highlight hazardous or potentially dangerous objects. The location of<br />

these lights will be as depicted on the Drawings or requested in the field<br />

by the CPM. Obstruction lights <strong>and</strong> barricades shall not be located within<br />

runway, taxiway or taxi lane obstacle clearance areas.<br />

2. The limits of construction, material storage area, plant site, equipment<br />

storage area, parking area <strong>and</strong> other areas defined as required for the<br />

CONTRACTOR’s exclusive use during construction shall be marked by<br />

the CONTRACTOR. The CONTRACTOR may erect <strong>and</strong> maintain around<br />

the perimeter of these areas suitable marking <strong>and</strong> warning devices visible<br />

for day/night use. Temporary fencing, barricades, flagging <strong>and</strong>/or flashing<br />

warning lights will be required at critical access points. Type of marking<br />

<strong>and</strong> warning devices shall be approved by CPM. Open trenches,<br />

excavations <strong>and</strong> stockpiled materials shall be permanently marked with<br />

flags <strong>and</strong> lighted by approved light units during hours of reduced visibility<br />

<strong>and</strong> darkness. No separate pay item is included for this Work <strong>and</strong> all<br />

costs must be included in the Lump Sum Bid.<br />

J. As designated on the Drawings, the CONTRACTOR shall erect <strong>and</strong> maintain<br />

Section 01540 Construction Plan <strong>and</strong> Safety Requirements Page 101