DIVISION 1 SPECIFICATIONS<br />

SECTION 01560 PREVENTION, CONTORL AND ABATEMENT<br />

OF EROSION AND WATER POLLUTION CONTROL<br />

Exhibit 2<br />

Page 318 of 379<br />

PART 1 - GENERAL<br />

1.01 DESCRIPTION<br />

A. Includes requirements for prevention, control <strong>and</strong> abatement of erosion situation<br />

<strong>and</strong> water pollution resulting from the construction of the Project until Final<br />

Completion <strong>and</strong> Acceptance.<br />

B. All applicable provisions of local codes concerning grading, filling, excavation,<br />

<strong>and</strong> soil removal shall be complied with.<br />

1.02 PERMITS<br />

A. It shall be the responsibility of the CONTRACTOR to obtain all Federal, State, <strong>and</strong><br />

local permits <strong>and</strong> to conduct his Work in the manner designated by all applicable<br />

permits. Violations of any permit by the CONTRACTOR will in no way involve the<br />

<strong>COUNTY</strong> regardless of who obtained the permit initially.<br />

1.03 ECOLOGICAL REQUIREMENTS<br />

A. Take sufficient precautions to prevent pollution of streams, canals, lakes,<br />

reservoirs <strong>and</strong> other water impoundments with fuels, oils, bitumens, calcium<br />

chloride or other harmful materials. Also, conduct <strong>and</strong> schedule operations so as<br />

to avoid interference with movement of migratory fish. No residue from dust<br />

collectors or washers shall be dumped into any live stream.<br />

B. Construction operations in rivers, streams, lakes, tidal waters, reservoirs, canals<br />

<strong>and</strong> other water impoundments shall be restricted to those areas where it is<br />

necessary to perform filling or excavation to accomplish the Work shown in the<br />

plans <strong>and</strong> to those areas which must be entered to construct temporary or<br />

permanent structures. As soon as conditions permit, rivers, stream, <strong>and</strong><br />

impoundments shall be properly cleared of all obstructions placed therein or<br />

caused by construction operations.<br />

C. Except as necessary for construction, <strong>and</strong> approved by the CPM, excavated<br />

material shall not be deposited in rivers, streams, canals or impoundments, or in<br />

a position close enough thereto to be washed away by high water or runoff.<br />

D. Do not disturb l<strong>and</strong>s or waters outside the limits of construction except as may be<br />

found necessary <strong>and</strong> authorized by the CPM.<br />

1.04 SCHEDULING/COORDINATION<br />

A. Clearing <strong>and</strong> grubbing shall be scheduled <strong>and</strong> performed that grading operations<br />

can follow immediately thereafter; grading operations shall be so scheduled <strong>and</strong><br />

performed that permanent erosion control features can follow immediately<br />

thereafter if conditions on the project permit.<br />

Section 01560 Prevention, Control <strong>and</strong> Abatement Page 113<br />

of Erosion <strong>and</strong> Water Pollution Control