DIVISION 1 SPECIFICATIONS<br />

SECTION 01315 PROGRESS SCHEDULES (COMPUTERIZED CPM)<br />

1.05 PREPARATION GUIDELINES<br />

A. The Baseline Schedule shall represent a practical plan to complete the work<br />

within the Contract Time.<br />

1. A schedule extending beyond the Contract Time will not be acceptable.<br />

2. A schedule showing the work completed in less than the Contract Time<br />

may be found by the CPM to be impractical.<br />

3. A schedule found by the CPM to be impractical for the preceding reason<br />

or any other reason will be revised by the CONTRACTOR <strong>and</strong><br />

resubmitted.<br />

4. A schedule showing the work completed in less than the Contract Time,<br />

which is found to be practical by the CPM, will be considered to have<br />

float. Float is the time <strong>between</strong> the scheduled completion of the work <strong>and</strong><br />

the contract Substantial Completion date.<br />

B. The Updated Progress Schedule shall:<br />

1. Be in sufficient detail to assure adequate planning <strong>and</strong> execution of the<br />

work.<br />

2. Be suitable, in the judgment of the CPM, to allow monitoring <strong>and</strong><br />

evaluation of progress in the performance of the Work.<br />

3. Be a calendar time-scaled logic diagram with a graphical layout<br />

illustrating logic ties with an accompanied activity listing identifying<br />

detailed predecessors <strong>and</strong> successors.<br />

4. Include time for the CPM <strong>and</strong> the CONSULTANT to review submittals or<br />

inspect the work.<br />

5. Identify the activities, which constitute the controlling items of work or<br />

critical path.<br />

C. COST CORRELATION - EARNED VALUE ANALYSIS (Not Used)<br />

1.06 SCHEDULE SUBMITTALS<br />

A. GENERAL SCHEDULE SUBMITTAL FORMAT:<br />

1. Logic drawings shall be submitted flat (11” x 17”) <strong>and</strong> reproducible as<br />

copies without loss of legibility. Size of plot <strong>and</strong> number of copies shall be<br />

at the discretion of the CPM.<br />

2. Hard copies of listings shall be prepared on separate sheets of 11” x 17”<br />

or legal size paper; include three (3) copies of each report.<br />

3. Electronic Format: All project files in original file format, as well as pdf file<br />

format, shall be copied <strong>and</strong> submitted on a (CD) compact disk. A project<br />

CD shall accompany all CONTRACTOR submissions.<br />

B. PRELIMINARY BASELINE SCHEDULE<br />

Exhibit 2<br />

Page 262 of 379<br />

1. Within twenty-one (21) calendar days after date of Contract Award<br />

Notice-to-Proceed, CONTRACTOR shall provide a Preliminary Baseline<br />

Schedule that shall be used to monitor the progress of Work during<br />

Section 01315 Progress Schedule (Computerized CPM) Page 57