DIVISION 1 SPECIFICATIONS<br />

SECTION 1045 CUTTING AND PATCHING<br />

Exhibit 2<br />

Page 218 of 379<br />

PART 1 - GENERAL<br />

1.01 Description<br />

A. Cutting <strong>and</strong> patching includes cutting into existing construction to provide for<br />

installation or performance of other Work, subsequent fitting, <strong>and</strong> patching<br />

required to restore surfaces to original condition.<br />

B. Proceed with cutting <strong>and</strong> patching at earliest feasible time <strong>and</strong> complete Work<br />

without delay except when work will impact traffic lanes, written approval by the<br />

CPM shall be obtained at least 72 hrs before impacting traffic lanes.<br />

C. Execute cutting, fitting, <strong>and</strong> patching, including attendant excavation <strong>and</strong> backfill,<br />

required to perform Work <strong>and</strong> to:<br />

1. Make several parts fit together properly.<br />

2. Uncover portions of Work to make provisions for installation of ill-timed<br />

Work.<br />

3. Remove <strong>and</strong> replace defective Work.<br />

4. Remove <strong>and</strong> replace Work not conforming to requirements of Contract<br />

Documents.<br />

5. Remove samples of installed Work as required for testing.<br />

6. Make routine penetrations of non-structural surfaces for installation of<br />

piping <strong>and</strong> electrical conduit.<br />

7. Uncover Work to allow for CPM’s observation of covered Work, which has<br />

been covered prior to required observation of CPM.<br />

D. Cutting <strong>and</strong> patching performed during manufacture of products, or during initial<br />

fabrication, erection or installation processes is not considered to be cutting <strong>and</strong><br />

patching. Drilling of holes to install fasteners <strong>and</strong> similar operations are also not<br />

considered to be cutting <strong>and</strong> patching.<br />

E. Refer to other sections of Specifications for specified cutting <strong>and</strong> patching<br />

requirement <strong>and</strong> limitations applicable to individual units of Work.<br />

F. Do not cut <strong>and</strong> patch the following categories of Work, without CPM’s written<br />

acceptance of procedures:<br />

1. Structural steel.<br />

2. Miscellaneous structural metals, including lintels, equipment supports,<br />

stair systems, <strong>and</strong> similar categories of Work.<br />

3. Structural concrete.<br />

Section 01045 Cutting <strong>and</strong> Patching Page 13