DIVISION 1 SPECIFICATIONS<br />

SECTION 01040 PROJECT COORDINATION<br />

Exhibit 2<br />

Page 216 of 379<br />

B. In addition to specific coordination <strong>and</strong> pre-installation meetings for each element<br />

of work, <strong>and</strong> other regular project meetings for other purposes, hold general<br />

progress meetings at least every week with time coordinated with preparation of<br />

payment request. Review present <strong>and</strong> future needs including interface<br />

requirements, time, sequences, deliveries, access, site utilization, temporary<br />

facilities <strong>and</strong> services, hours of work, hazards <strong>and</strong> risks, housekeeping, change<br />

orders <strong>and</strong> documentation of information for payment requests.<br />

C. Discuss whether each element of current Work is ahead of schedule, on time, or<br />

behind schedule in relation with updated progress schedule. Determine how<br />

behind-schedule Work will be expedited <strong>and</strong> secure commitments from parties<br />

involved. Discuss whether schedule revisions are required to ensure that current<br />

Work <strong>and</strong> subsequent Work will be completed within Contract Time.<br />

D. Review everything of significance, which could affect progress of work.<br />

E. The CPM records results of the meeting <strong>and</strong> distributes copies to everyone in<br />

attendance <strong>and</strong> to others affected by decisions or actions resulting from each<br />

meeting.<br />

1.04 PRE-INSTALLATION CONFERENCES<br />

Record significant discussions of each conference, <strong>and</strong> record agreements <strong>and</strong><br />

disagreements, along with final plan of action. Distribute record of meeting<br />

promptly to everyone concerned, including CPM <strong>and</strong> CONSULTANT.<br />

1.05 REPORTING AND SCHEDULES<br />

A. Within three (3) days after each meeting date, the CPM shall distribute a brief<br />

summary, in narrative form, of progress of Work since previous meeting <strong>and</strong><br />

report.<br />

B. Schedule Updating:<br />

1.06 SPECIAL REPORTS<br />

The CONTRACTOR shall update schedules weekly to include revisions resulting<br />

from information discussed at meetings held since the previous schedule update.<br />

The CONTRACTOR shall distribute a tabular, early start / total float report to the<br />

CPM.<br />

A. CONTRACTOR shall prepare a report that provides information on the value<br />

engineering <strong>and</strong> constructability review phase of the Pre-Construction work. The<br />

report will, among other things, identify: the Work items that value engineering<br />

Section 01040 Project Coordination Page 11