22.01.2015 Views

Attachment 1: Specifications - Metropolitan Washington Airports ...

Attachment 1: Specifications - Metropolitan Washington Airports ...

Attachment 1: Specifications - Metropolitan Washington Airports ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

DCA TERMINAL A IMPROVEMENTS (NEAR TERM) 10 AUGUST 2012<br />

TASK ORDER 03: LOBBY IMPROVEMENTS – PKG 4 - CURBSIDE CHECK-IN<br />

RONALD REAGAN WASHINGTON NATIONAL AIRPORT<br />

PROJECT DT1203<br />

a. Differentiate between potential items stored on-site and items stored off-site.<br />

Include evidence of insurance or bonded warehousing if required.<br />

6. Provide separate line items in the Schedule of Values for initial cost of materials, for each<br />

subsequent stage of completion, and for total installed value of that part of the Work..<br />

7. Each item in the Schedule of Values and Application for Payment shall be complete.<br />

Include total cost and proportionate share of general overhead and profit for each item.<br />

a. At COTR’s option, temporary facilities and other major cost items that are not<br />

direct cost of actual work-in-place may be shown either as separate line items in<br />

the Schedule of Values or distributed as general overhead expense.<br />

8. Schedule Updating: Update and resubmit the Schedule of Values with the next<br />

Applications for Payment when Contract Modifications result in a change in the Contract<br />

Price.<br />

1.5 APPLICATION FOR PAYMENT<br />

A. Each Application for Payment shall be consistent with previous applications and payments as<br />

certified by Contracting Officer and paid for by The Authority.<br />

1. Initial Application for Payment, Application for Payment at time of Substantial<br />

Completion, and final Application for Payment involve additional requirements.<br />

B. Payment Application Times: Application for Payment shall coincide with CPM schedule<br />

monthly update, or as otherwise indicated in the Agreement between The Authority and<br />

Contractor. The period covered by each Application for Payment starts on the day following<br />

the end of the preceding period and shall not exceed one calendar month, unless otherwise<br />

approved by COTR.<br />

C. Payment Application Forms: Use forms provided by the Contracting Officer, but supplied by<br />

COTR, for Application for Payment.<br />

D. Application Preparation: Complete every entry on form. Notarize and execute by a person<br />

authorized to sign legal documents on behalf of Contractor. The Authority will return<br />

incomplete applications without action.<br />

1. Entries shall match data on the Schedule of Values and Contractor's Construction<br />

Schedule. Use updated schedules if revisions were made.<br />

2. Include amounts of Contract Modifications issued before last day of the construction<br />

period covered by application.<br />

E. Transmittal: Submit one original and four copies of Application for Payment to the address<br />

indicated in the Section VII - Contract Provision, Paragraph 04.B, each one signed and<br />

notarized. Include waivers of lien and similar attachments if required.<br />

APPLICATION FOR PAYMENT 01 29 00 - 3

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!