DCA TERMINAL A IMPROVEMENTS (NEAR TERM)10 AUGUST 2012<br />

TASK ORDER 03: LOBBY IMPROVEMENTS – PKG 4 -CURBSIDE CHECK-IN<br />

RONALD REAGAN WASHINGTON NATIONAL AIRPORT<br />

PROJECT DT1203<br />

for The Authority’s review and approval 60 calendar days prior to the start-up of the<br />

testing.<br />

3. The Test Plan shall also include the recording of the following information per<br />

subsystem(s), conveyor and device during the inspection and testing of the system(s). All<br />

actual speeds and motor currents shall be measured with the system(s) in a “no-load” and<br />

“load” condition, i.e., all conveyors of BHS running but without and with bags.<br />

Contractor shall complete all recording in the Test Plan.<br />

a. Main Feeds:<br />

1) Fuse size per phase.<br />

2) Actual amperage per phase.<br />

b. Transformers:<br />

1) Fuse size per phase.<br />

2) Actual amperage per phase.<br />

c. Conveyor/Device Speed:<br />

1) Actual center line speed of conveyor/device.<br />

d. Motor Name Plate Data:<br />

1) Manufacturer<br />

2) Horsepower<br />

3) Nameplate Current<br />

4) Voltage<br />

5) Phase<br />

6) RPM<br />

7) Frame Size<br />

8) Type<br />

9) Hertz<br />

10) NEMA Design<br />

11) Service Factor<br />

12) Insulation Class<br />

13) Insulation Type<br />

e. Fuse size per phase.<br />

f. Actual amperage per phase.<br />

g. Belt slippage under load.<br />

4. The above test results and information, final dynamic and static test results shall be<br />

included in the final O & M Manuals for reference information.<br />

5. The material including test bags to be used for the all necessary tests, plus personnel to<br />

handle it, shall be provided by the BHSC. The BHSC shall have all personnel and a<br />

representative identified by the COTR “on site” during all periods of the system(s)<br />

Inspection and Testing. All tests shall be conducted with bags, tubs, blocks, etc. or<br />

combinations of these items; and at the COTR’s option with laded cartons to supplement<br />

available baggage. The BHSC shall identify a list of items in the test plan.<br />

BAGGAGE HANDLING EQUIPMENT 34 77 16 - 56