84 <strong>100</strong> METHODS FOR TOTAL QUALITY MANAGEMENT<br />

If any activity has a float of, say, 3 days, then if it took up to 3 days longer<br />

than planned it would not affect the project duration. However, a <strong>de</strong>lay<br />

longer than this would <strong>de</strong>lay the project's completion.<br />

In our example, the float for each activity is as follows:<br />

Activity<br />

Float<br />

A<br />

o<br />

B<br />

o<br />

C<br />

5<br />

D<br />

o<br />

E<br />

5<br />

F<br />

o<br />

G<br />

5<br />

H<br />

o<br />

If an activity has a float of zero it is a critical activity. Any <strong>de</strong>lay in a<br />

critical activity will <strong>de</strong>lay the overall project. Paths through the network<br />

composed only of critical activities are known as critical paths.<br />

The critical path is therefore:<br />

ABDFH<br />

Reference<br />

D.R. An<strong>de</strong>rson, D.J. Sweeney and T.A. Williams (1994) An Introduction to Management<br />

Sciences. New York: West.