Tamil Research Institute<br />

RAPID TECHNO-ECONOMIC FEASIBILITY REPORT FOR<br />

DEVELOPMENT OF COLACHEL PORT AT TAMILNADU<br />

FINAL REPORT<br />

• Police station<br />

• Fire station<br />

• Customs<br />

The container terminal includes:<br />

• Maintenance workshop<br />

• Marine operations building<br />

• Administration building<br />

• Entry/Exit gates<br />

Some other buildings might be added in future stages of the design process.<br />

9.7. PORT PLANNING FOR PHASES 2, 3 AND FUTURE EXTENSION<br />

When traffic is near Phase 1 capacity, Phase 2 expansion must be developed to service the new traffic.<br />

Phase 2, planned from 2021 to 2025, consists of a 2,000 m extension of the container berth and another 92 Ha<br />

for container terminals, and a new 400 m berth and 9 Ha for a new coal terminal on the west side of the port.<br />

Container terminal capacity in this phase is around 5.6 million TEUs per year and more than 10 M tonnes of solid<br />

bulk (coal).<br />

Phase 3, planned from 2026 to 2030 consist on extending the container terminal by 1,200 m of berth and 95 Ha<br />

of yard. This will mean 4,000 m of total berth line which gives a total capacity of 8 million TEUs per year. Regarding<br />

solid bulk terminal, it will be duplicated to a total berth of 800 m and a total stockyard of 18 Ha.<br />

Both the Phase 2 and Phase 3 coal berths have been planned to be built with the possibility to be converted into a<br />

container berth in case of the container traffic raises beyond expected rates and coal traffic below expected.<br />

The following table shows the main figures and characteristics for the three analyzed phases of the port (cumulative<br />

figures):<br />

Description<br />

Units<br />

Phase 1<br />

(2018-2020)<br />

Phase 2<br />

(2021-2025)<br />

Phase 3<br />

(2026-2030)<br />

Container Terminal Capacity TEU 1,606,590 5,623,064 8,032,949<br />

Bulk Capacity (coal) M. Ton 0.00 3.30 6.60<br />

Berths (total) m 1,400 3,800 5,400<br />

Container m 800 2,800 4,000<br />

Multipurpose m 400 400 400<br />

CP1832-FR-CP-FinalReportRevised-Report-Ed1.docx 157<br />

www.tamilri.com