28.11.2017 Views

Enayam Port

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Tamil Research Institute<br />

RAPID TECHNO-ECONOMIC FEASIBILITY REPORT FOR<br />

DEVELOPMENT OF COLACHEL PORT AT TAMILNADU<br />

FINAL REPORT<br />

12. ESTIMATION OF PROJECT CAPITAL COST<br />

12.1. PRINCIPLES FOR COST ESTIMATION<br />

This cost estimates are calculated in order to have an input on the CAPEX of the project and to be able to calculate its<br />

financial feasibility.<br />

The following assumptions have been used:<br />

• All costs are presented Rupees.<br />

• Mobilization and demobilization costs are included in respective entities.<br />

• Land costs have been obtained by requesting information from authorities and private companies. A deeper<br />

analysis must be developed to confirm these costs.<br />

• Engineering and project management is added as 7.5 % of the project costs.<br />

• Besides, 15% of the project costs have been included for contingencies.<br />

Costs and rates are based on similar projects developed by TYPSA and BCG, and marine projects of south India,<br />

like Colachel fishing harbour, currently in progress. Some of the rates are “macro-rates”, which means a rough<br />

estimate of a major unity.<br />

Cost estimates have been broken down in the following sections:<br />

Preliminaries<br />

This section includes all the preliminary studies and surveys (e.g. bathymetric or topographic surveys previous to the<br />

beginning of the construction), and some other works required before the main works begin. One important<br />

preliminary work is the temporary berthing facility which will allow the construction of the breakwater by maritime<br />

means.<br />

Breakwaters<br />

As explained earlier, both rubble mound and vertical breakwaters have been proposed following a cost saving<br />

criteria. The following considerations have been assumed for rubble mound breakwaters:<br />

• Rock layers porosity: 0.370<br />

• Concrete cubes layer porosity: 0.470<br />

• Accropods layers porosity: 0.491<br />

Regarding vertical breakwaters, the following assumptions have been taken for caisson construction and installation:<br />

• 20% of total volume of caisson is reinforced concrete and 80% is sand fill.<br />

• Reinforcement steel rate is 100 kg/m 3 of concrete.<br />

Berths<br />

The cost estimates have been made considering the basic design of an open pile berthing structure, assuming a 9 m<br />

x 9 m grid and mean length of 35 m for piles, with stone pitching as slope protection underneath the berth. Also, a<br />

mean thickness of 1.0 m for reinforced concrete superstructure has been considered, with a reinforcement steel rate of<br />

120 kg/m 3 .<br />

CP1832-FR-CP-FinalReportRevised-Report-Ed1.docx 170<br />

www.tamilri.com

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!