Tamil Research Institute<br />

RAPID TECHNO-ECONOMIC FEASIBILITY REPORT FOR DEVELOPMENT OF<br />

COLACHEL PORT AT TAMILNADU<br />

FINAL REPORT<br />

Nº Activity<br />

Relevant<br />

Environmental<br />

Components to be<br />

affected<br />

Likely Impacts<br />

Proposed Mitigation Measures<br />

Responsible Agency for<br />

Implementation<br />

9 Breakwaters Shoreline<br />

10<br />

Operation of <strong>Port</strong> Marine Environment Natural Hazards .<br />

<br />

<br />

OPERATIONAL PHASE<br />

Changes in shoreline adjacent to <strong>Port</strong>.<br />

Erosion/accretion<br />

Loosing of beach area Impact on houses/<br />

structures along the coast<br />

<br />

<br />

<br />

<br />

<br />

facilities, drainage and solid waste<br />

management facilities) should be constructed.<br />

Fishermen using the beaches for mussel (brown<br />

mussel) collection and for shore seine in the<br />

project footprint area will be compensated<br />

with either alternate employment or to be<br />

suitably integrated to the new fishing harbour<br />

/port activities<br />

Mathematical model to study and predict the<br />

shoreline changes due to the presence of<br />

breakwaters should be carried out<br />

Shoreline monitoring should be carried. Final<br />

Shoreline Impact Management plan must be<br />

prepared in consultation with agencies like<br />

CESS/INCOIS, NGO and local bodies and<br />

will implemented.<br />

Suitable Shoreline protection measures will be<br />

implemented based on the observations<br />

Disaster Management Plan (DMP) should be<br />

prepared; Manager (EHS) will act as the<br />

overall in-charge of the control of educative,<br />

protective and rehabilitation activities to ensure<br />

least damage to life and property.<br />

<strong>Port</strong> Authority /<br />

<strong>Port</strong> Authority /<br />

Table 57 EMP <strong>Port</strong> Construction and Operation Potential Impacts and Mitigation Measures of Various Project Activities.<br />

CP1832-FR-AX-05-CP-Initial Environmental Examination-Ed4.docx AX05 - 170<br />

www.tamilri.com