28.11.2017 Views

Enayam Port

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Tamil Research Institute<br />

RAPID TECHNO-ECONOMIC FEASIBILITY REPORT FOR<br />

DEVELOPMENT OF COLACHEL PORT AT TAMILNADU<br />

FINAL REPORT<br />

7. CONCLUSIONS AND RECOMENDATIONS<br />

The development of proposed Colachel <strong>Port</strong> at Tamil Nadu offers an efficient and cost effective supply<br />

chain/value proposition to the local importers and exporters. This could trigger a new set of opportunities as<br />

induced developments.<br />

Initially, 4 alternatives were considered for the location of the port infrastructure. After a multicriteria analysis<br />

where the environmental and social factors played a key role together with the rest of the project components<br />

<strong>Enayam</strong>, was considered as the best rated alternative location, with the lowest impact, while the worst rated<br />

one, with the highest impact, is Colachel. Kanyakumari and Manavalakurichi obtained similar intermediate<br />

ratings.<br />

The <strong>Enayam</strong> location has lower environmental impacts than the others with respect to dredging, cultural sites and<br />

its low impact on property due to its low population. <strong>Port</strong> expansion will not need a wide extra inland area since<br />

the land reclamation area will provide room for port facilities and industries.<br />

Dedicated roadway and railway connectivity proposed for the Colachel-<strong>Enayam</strong> port would provide access to<br />

the major existing road and railway network which offers an efficient and cost effective supply chain/value<br />

proposition to the local importers and exporters in the State of Tamil Nadu. Employment opportunities to the local<br />

people would rise for skilled, semi-skilled and unskilled work force during the construction and operation phases<br />

All this will accomplish one of the main aims of the proposed port project; which is to bring significant socioeconomic<br />

benefits to the local people and also to the region as a whole, bringing significant benefits to local<br />

people and to the region as a whole and positive impact on the socioeconomic conditions of the project region<br />

and the whole Tamil Nadu State.<br />

However the activities during the construction phase might have some other potential impacts on the socioeconomic<br />

environment which includes dredging, reclamation, transportation of quarrying materials, construction<br />

of terminals and breakwater as well as establishment of labour camps. During the operation phase, the operation<br />

of terminals, marine traffic, road & rail traffic and establishment of labour/employee colony might have potential<br />

impact on the socio-economic environment of that region. However, as the port is planned to be developed<br />

entirely on the reclaimed land, no land acquisition is envisaged for the port development.<br />

However, a total number of 427 properties would be directly affected by the implementation of the railway line<br />

and road connections. Apart from that, being an international harbour, the port would require additional basic<br />

infrastructure facilities, administrative buildings cruise and navy operations facilities, , warehouse, residential<br />

areas, truck parking areas . Hence, backup areas in the immediate vicinity will be required in the future for<br />

developing other further facilities.<br />

As for the impact onto the current environmental conditions the port activities and their impacts on the<br />

environmental and social attributes during the development and operation phase have been discussed in detail.<br />

It was concluded that most of the negative effects that may take place with the implementation of the project<br />

could be mitigated with the adoption of appropriate mitigation measures, both in construction and operational<br />

phase and the effective implementation of the proposed environmental management and monitoring<br />

programmes.<br />

A preliminary environmental budget plan to address all environmental management requirements has been<br />

estimated, the budgetary provision required to achieve. Some of the key areas identified are the following:<br />

CP1832-FR-AX-05-CP-Initial Environmental Examination-Ed4.docx AX05 - 180 180<br />

www.tamilri.com

Hooray! Your file is uploaded and ready to be published.

Saved successfully!