RAPID TECHNO-ECONOMIC FEASIBILITY REPORT FOR DEVELOPMENT<br />

OF COLACHEL PORT AT TAMILNADU<br />

FINAL REPORT<br />

(all figures in INR crores)<br />

Component Phase 1 Phase 2 Phase 3<br />

Preliminaries 23.6 2.8 2.8<br />

Breakwaters 1,124.4 611.5 439.2<br />

Berth 429.2 1,123.3 895.5<br />

Dredging and Reclamation 809.1 1,173.3 638.6<br />

Yards 347.3 633.2 358.7<br />

Equipments 1,247.4 3,209.9 2,025.5<br />

Buildings 27.4 17.6 8.8<br />

Network and Utilities 131.0 52.9 35.3<br />

Connectivity 273.4 0.0 0.0<br />

Land Acquisition 70.7 0.0 0.0<br />

<strong>Port</strong> Crafts 0.0 0.0 0.0<br />

Total Civil Cost 4,483.6 6,824.5 4,404.3<br />

Engineering and project management 336.3 511.8 330.3<br />

Provision for contingencies 672.5 1,023.7 660.6<br />

Escalation 347.5 2,237.3 3,173.1<br />

Total Construction Cost 5,839.8 10,597.3 8,568.4<br />

Interest During Construction 689.3 877.7 823.3<br />

Syndication Fees 46.0 61.9 66.2<br />

Total Project Cost for Phase 6,575.2 11,536.9 9,457.9<br />

Table 43: Summary of Phase-wise Project Cost<br />

183<br />