RAPID TECHNO-ECONOMIC FEASIBILITY REPORT FOR<br />

DEVELOPMENT OF COLACHEL PORT AT TAMILNADU<br />

FINAL REPORT<br />

Ancillary vessels m 200 200 200<br />

Solid bulk m 0 400 800<br />

Terminals/Yards/Areas Ha 93 249 379<br />

Container Ha 41 133 228<br />

General services & multi- purpose Ha 19 19 19<br />

Solid bulk terminal Ha 0 9 20<br />

Industrial area Ha 33 88 112<br />

Breakwaters m 4,639 7,237 8,904<br />

Rubble mound m 2,133 2,842 3,402<br />

Vertical m 2,506 4,395 5,502<br />

Dredging and reclamation<br />

Dredging Cu.m 6,819,280 13,151,903 14,973,161<br />

Reclamation Cu.m 3,303,993 12,866,152 19,261,679<br />

Table 39: Main figures for Phase 1, 2 and 3 (cumulative figures)<br />

A future extension beyond Phase 3 is possible in order to increase the port capacity to 16 million TEU. This extension<br />

can be made converting the vertical breakwater into a berth line and a new landfill area shall be developed<br />

seawards.<br />

CP1832-FR-CP-FinalReportRevised-Report-Ed1.docx 158<br />

www.tamilri.com