• Option 1 was discussed as the ideal program <strong>for</strong> the Southside development.<br />
This location would house the staff required <strong>for</strong> the pr<strong>of</strong>essional<br />
development component. Peter Zanoni will provide FP&C with the projected<br />
staffing requirements so that this component may be sized appropriately.<br />
• Option 2 was decided to be a good basis <strong>for</strong> the Northside program, with<br />
some modifications.<br />
• <strong>The</strong> group decided that some <strong>of</strong> the instructional spaces could be<br />
utilized in the short-term <strong>for</strong> the pr<strong>of</strong>essional development aspects,<br />
such as training and the library.<br />
• <strong>The</strong> original 25 classrooms would be constructed. However, only the<br />
number required to manage the initial 350 students (approx. 18<br />
classrooms) would be fit out <strong>for</strong> this purpose. <strong>The</strong> remaining<br />
classrooms (7) would be utilized in the short-term <strong>for</strong> training room,<br />
library and gross motor skills area.<br />
• As the program grows to 500 students, these functions would be<br />
relocated into portables outside the building. <strong>The</strong> remaining<br />
classrooms would then be renovated (through furniture change) <strong>for</strong><br />
the children’s instruction.<br />
• Outdoor playground area was also discussed. It is required by state licensing<br />
regulations that play area (min. 80sf per child) be provided <strong>for</strong> at least 25%<br />
<strong>of</strong> the projected capacity <strong>of</strong> the daycare. This resulted in the need <strong>for</strong> at least<br />
10,000sf <strong>of</strong> playground area <strong>for</strong> 125 children (25% <strong>of</strong> 500 max. capacity).<br />
• Due to the difficulty <strong>of</strong> controlling such a large amount <strong>of</strong><br />
playground area and this number <strong>of</strong> children at one time, it was<br />
decided that multiple smaller playgrounds should be provided,<br />
instead <strong>of</strong> one large playground. This would also allow <strong>for</strong> the<br />
variety <strong>of</strong> playscape equipment which had been discussed in<br />
previous meetings.<br />
• Although not required by licensing regulation, the Nurse’s Office is a desired<br />
component <strong>of</strong> the program and should be included.<br />
• Food service/distribution was discussed briefly. Food will be catered and<br />
delivered to the building kitchen. This will only be a prep/warming kitchen<br />
and will not be full-service. Meals will be stored here and distributed to the<br />
individual classrooms throughout the day.<br />
• An area needs to be provided <strong>for</strong> building recycling and trash collection.<br />
• <strong>The</strong> amount <strong>of</strong> parking at each center, specifically the Southside, was<br />
discussed briefly. FP&C agreed to provide the parking counts once the space<br />
list was updated with revisions from this meeting.<br />
• <strong>The</strong> next steps were discussed.<br />
• FP&C will provide a revised space list by the end <strong>of</strong> business July<br />
20. An adjacency diagram showing potential relationships between<br />
spaces will be prepared early the following week.<br />
• Peter Zanoni will provide an updated count/projection <strong>for</strong> the<br />
pr<strong>of</strong>essional development administration component to be included<br />
in the space list.<br />
<strong>City</strong> <strong>of</strong> <strong>San</strong> <strong>Antonio</strong> Early Childhood Centers <strong>of</strong> Excellence<br />
Progress Meeting with Co<strong>SA</strong> Assistant <strong>City</strong> Manager and Ed. Policy Administrator Page 2<br />
July 20, 2012