<strong>DOH</strong> CUSTOMIZED PROCUREMENT MANUAL VOLUME 4 2010<br />

FORMS OF PERFORMANCE SECURITY<br />

a. Cash, cashier’s/manager’s Check issued by a<br />

Universal or Commercial Bank.<br />

b. Bank draft/guarantee or irrevocable letter <strong>of</strong><br />

credit issued by a Universal or Commercial Bank:<br />

Provided, however, that it shall be confirmed or<br />

au<strong>the</strong>nticated by a Universal or Commercial Bank,<br />

if issued by a <strong>for</strong>eign bank.<br />

c. Surety bond callable upon demand issued by a<br />

surety or insurance company duly certified by <strong>the</strong><br />

Insurance Commission as authorized to issue<br />

such security.<br />

AMOUNT OF PERFROMANCE SECURITY<br />

(EQUAL TO PERCENTAGE OF THE ABC)<br />

Five percent (5%)<br />

Thirty percent (30%)<br />

d. Any combination <strong>of</strong> <strong>the</strong> <strong>for</strong>egoing. Proportionate to share <strong>of</strong> <strong>for</strong>m with respect to total<br />

amount <strong>of</strong> security<br />

3.8.3 Who determines <strong>the</strong> <strong>for</strong>m?<br />

The procuring entity cannot limit <strong>the</strong> allowable <strong>for</strong>ms <strong>of</strong> per<strong>for</strong>mance security<br />

provided under <strong>the</strong> revised IRR <strong>of</strong> R.A. 9184 nor and modify <strong>the</strong> respective<br />

amounts <strong>the</strong>re<strong>of</strong>. The winning bidder must choose which among <strong>the</strong> allowable<br />

<strong>for</strong>ms it shall submit.<br />

3.8.4 Change in Per<strong>for</strong>mance Security in case <strong>of</strong> contract price changes<br />

In case <strong>of</strong> a reduction in <strong>the</strong> contract value, or, in <strong>the</strong> case <strong>of</strong> <strong>procurement</strong> <strong>of</strong><br />

infrastructure projects, <strong>for</strong> partially completed works under <strong>the</strong> contract which are<br />

usable and accepted by <strong>the</strong> GOP, and <strong>the</strong> use <strong>of</strong> which, in <strong>the</strong> judgment <strong>of</strong> <strong>the</strong><br />

implementing agency or <strong>the</strong> procuring entity, will not affect <strong>the</strong> structural integrity<br />

<strong>of</strong> <strong>the</strong> entire project, <strong>the</strong> said agency or procuring entity shall allow a proportional<br />

reduction in <strong>the</strong> original per<strong>for</strong>mance security, provided that any such reduction is<br />

more than ten percent (10%) and that <strong>the</strong> aggregate <strong>of</strong> such reductions is not<br />

more than fifty percent (50%) <strong>of</strong> <strong>the</strong> original Per<strong>for</strong>mance Security (Section 39.7<br />

<strong>of</strong> <strong>the</strong> revised IRR).<br />

3.8.5 Release <strong>of</strong> Per<strong>for</strong>mance Security<br />

The per<strong>for</strong>mance security may be released by <strong>the</strong> procuring entity after <strong>the</strong><br />

issuance <strong>of</strong> <strong>the</strong> Certificate <strong>of</strong> Acceptance, subject to <strong>the</strong> following conditions:<br />

a. Procuring entity has no claims filed against <strong>the</strong> contract awardee or <strong>the</strong><br />

surety company;<br />

91