<strong>DOH</strong> CUSTOMIZED PROCUREMENT MANUAL VOLUME 4 2010<br />
FORMS OF PERFORMANCE SECURITY<br />
a. Cash, cashier’s/manager’s Check issued by a<br />
Universal or Commercial Bank.<br />
b. Bank draft/guarantee or irrevocable letter <strong>of</strong><br />
credit issued by a Universal or Commercial Bank:<br />
Provided, however, that it shall be confirmed or<br />
au<strong>the</strong>nticated by a Universal or Commercial Bank,<br />
if issued by a <strong>for</strong>eign bank.<br />
c. Surety bond callable upon demand issued by a<br />
surety or insurance company duly certified by <strong>the</strong><br />
Insurance Commission as authorized to issue<br />
such security.<br />
AMOUNT OF PERFROMANCE SECURITY<br />
(EQUAL TO PERCENTAGE OF THE ABC)<br />
Five percent (5%)<br />
Thirty percent (30%)<br />
d. Any combination <strong>of</strong> <strong>the</strong> <strong>for</strong>egoing. Proportionate to share <strong>of</strong> <strong>for</strong>m with respect to total<br />
amount <strong>of</strong> security<br />
3.8.3 Who determines <strong>the</strong> <strong>for</strong>m?<br />
The procuring entity cannot limit <strong>the</strong> allowable <strong>for</strong>ms <strong>of</strong> per<strong>for</strong>mance security<br />
provided under <strong>the</strong> revised IRR <strong>of</strong> R.A. 9184 nor and modify <strong>the</strong> respective<br />
amounts <strong>the</strong>re<strong>of</strong>. The winning bidder must choose which among <strong>the</strong> allowable<br />
<strong>for</strong>ms it shall submit.<br />
3.8.4 Change in Per<strong>for</strong>mance Security in case <strong>of</strong> contract price changes<br />
In case <strong>of</strong> a reduction in <strong>the</strong> contract value, or, in <strong>the</strong> case <strong>of</strong> <strong>procurement</strong> <strong>of</strong><br />
infrastructure projects, <strong>for</strong> partially completed works under <strong>the</strong> contract which are<br />
usable and accepted by <strong>the</strong> GOP, and <strong>the</strong> use <strong>of</strong> which, in <strong>the</strong> judgment <strong>of</strong> <strong>the</strong><br />
implementing agency or <strong>the</strong> procuring entity, will not affect <strong>the</strong> structural integrity<br />
<strong>of</strong> <strong>the</strong> entire project, <strong>the</strong> said agency or procuring entity shall allow a proportional<br />
reduction in <strong>the</strong> original per<strong>for</strong>mance security, provided that any such reduction is<br />
more than ten percent (10%) and that <strong>the</strong> aggregate <strong>of</strong> such reductions is not<br />
more than fifty percent (50%) <strong>of</strong> <strong>the</strong> original Per<strong>for</strong>mance Security (Section 39.7<br />
<strong>of</strong> <strong>the</strong> revised IRR).<br />
3.8.5 Release <strong>of</strong> Per<strong>for</strong>mance Security<br />
The per<strong>for</strong>mance security may be released by <strong>the</strong> procuring entity after <strong>the</strong><br />
issuance <strong>of</strong> <strong>the</strong> Certificate <strong>of</strong> Acceptance, subject to <strong>the</strong> following conditions:<br />
a. Procuring entity has no claims filed against <strong>the</strong> contract awardee or <strong>the</strong><br />
surety company;<br />