<strong>DOH</strong> CUSTOMIZED PROCUREMENT MANUAL VOLUME 4 2010<br />

3.7.3 Period <strong>of</strong> validity <strong>of</strong> Bids and Bid Security<br />

Bids and bid securities must be valid <strong>for</strong> a reasonable period <strong>of</strong> time as<br />

determined by <strong>the</strong> HOPE. This time period must be indicated in <strong>the</strong> bidding<br />

documents, but in no case should it exceed one hundred twenty (120) calendar<br />

days from <strong>the</strong> date <strong>of</strong> <strong>the</strong> opening <strong>of</strong> bids (Section 28.1 <strong>of</strong> <strong>the</strong> revised IRR).<br />

Should it become necessary to extend <strong>the</strong> validity <strong>of</strong> <strong>the</strong> bids and bid securities<br />

beyond one hundred twenty (120) calendar days, <strong>the</strong> procuring entity concerned<br />

shall request in writing all those who submitted bids <strong>for</strong> such extension be<strong>for</strong>e <strong>the</strong><br />

expiration date <strong>the</strong>re<strong>of</strong>. Bidders, however, shall have <strong>the</strong> right to refuse to grant<br />

such extension without <strong>for</strong>feiting <strong>the</strong>ir bid security (Section 28.2 <strong>of</strong> <strong>the</strong> revised<br />

IRR).<br />

3.7.4 Denomination<br />

The bid security must be denominated in Philippine Pesos and posted in favor <strong>of</strong><br />

<strong>the</strong> procuring entity (Section 27.3 <strong>of</strong> <strong>the</strong> revised IRR 27.3).<br />

3.7.5 Failure to submit Bid Security<br />

Failure to enclose <strong>the</strong> required bid security in <strong>the</strong> <strong>for</strong>m and amount prescribed<br />

herein shall automatically disqualify <strong>the</strong> bid concerned (Section 27.1 <strong>of</strong> <strong>the</strong><br />

revised IRR 27.1).<br />

3.7.6 Time to returned to bidders Bid Security<br />

Without prejudice to <strong>the</strong> provisions <strong>of</strong> <strong>the</strong> Act and <strong>the</strong> revised IRR on <strong>the</strong><br />

<strong>for</strong>feiture <strong>of</strong> bid securities, bid securities shall be returned only after <strong>the</strong> bidder<br />

with <strong>the</strong> HRRB has signed <strong>the</strong> contract and furnished <strong>the</strong> per<strong>for</strong>mance security,<br />

except to those declared by <strong>the</strong> BAC as failed or post-disqualified in accordance<br />

with <strong>the</strong> revised IRR <strong>of</strong> R.A. 9184, upon submission <strong>of</strong> a written waiver <strong>of</strong> <strong>the</strong>ir<br />

right to file a request <strong>for</strong> reconsideration and/or protest (Section 27.4 <strong>of</strong> <strong>the</strong><br />

revised IRR).<br />

In no case shall bid security be returned later than <strong>the</strong> expiration <strong>of</strong> <strong>the</strong> bid validity<br />

period indicated in <strong>the</strong> Bidding Documents, unless it has been extended in<br />

accordance with Section 28.2 <strong>of</strong> <strong>the</strong> revised IRR <strong>of</strong> R.A. 9184 (Section 27.5 <strong>of</strong><br />

<strong>the</strong> revised IRR).<br />

3.7.7 Forfeiture<br />

A bidder‟s bid security may be <strong>for</strong>feited when:<br />

a. The bidder withdraws its bid beyond <strong>the</strong> deadline;<br />

65